Construction Industry, Construction Law, Contract Administration

FIDIC Payment Provisions: The IPC Process, Withholding, Set-Off, and Late Payment Interest

Payment is the lifeblood of any construction project, yet the FIDIC payment mechanism — in both the 1999 and 2017 suites — is among the most technically demanding and frequently disputed aspects of contract administration. From the preparation of the Interim Payment Certificate (IPC) and the Engineer’s power to withhold or correct amounts, to the Employer’s right of set-off and the contractor’s entitlement to financing charges on late payments, the payment clauses contain traps for the unwary on all sides. Understanding precisely how the mechanism operates, and where it commonly fails, is essential for contractors, employers, and engineers alike.

Construction Industry, Construction Law, Contract Administration

Unforeseeable Ground Conditions Under FIDIC Sub-Clause 4.12: The Objective Test and What Contractors Must Prove

Ground conditions have derailed more construction projects — and generated more claims — than almost any other single factor. When a contractor breaks ground and encounters rock where soil surveys suggested soft earth, or strikes an abandoned utilities network that no map recorded, or finds groundwater at depths that make excavation a different project entirely, the question of who bears the cost is rarely straightforward. FIDIC Sub-Clause 4.12 is the contractual mechanism designed to answer that question — but its application turns on a deceptively difficult concept: what an “experienced contractor” could reasonably have foreseen. Understanding how that test works in practice is essential for every party operating under a FIDIC contract.

Construction Industry, Construction Law, Contract Administration

The FIDIC 2017 Claims Mechanism: Has the Time-Bar Beast Been Tamed?

Of all the contentious provisions in international construction contracts, few have generated more disputes — or more anxiety among contractors — than the 28-day notice requirement embedded in Clause 20.1 of the FIDIC 1999 suite. Known colloquially as the “time-bar,” this clause has been the graveyard of otherwise meritorious claims, wiping out entitlements worth millions of dollars on technical grounds entirely unrelated to the merits of the underlying claim.

Construction Industry, Construction Law, Contract Administration, Security of Payment, Statutory Adjudication

Reflecting on the Second Edition of International Contractual and Statutory Adjudication

By Dr Samer Skaik

Over the past decade, my work in construction law and adjudication has consistently reinforced one reality: adjudication has become a cornerstone of modern dispute resolution across the global construction industry. It has therefore been a privilege to contribute to the Second Edition of International Contractual and Statutory Adjudication, as an Assistant Editor as well as a Contributor of six chapters, bringing together perspectives from across multiple jurisdictions. The book is edited by the prominent author & practitioner Andrew Burr with editorial assistance from Narudee Chuekitkumchorn and myself.

Construction Industry, Construction Law, Contract Administration, Project Management

Decoding Concurrent Delay: The SCL Protocol and Employer Responsibility

Delays in construction and infrastructure projects are almost an inevitability. But what happens when multiple delays hit at once, and some are the client’s fault while others lie with the contractor? This is the tricky terrain of concurrent delay, a concept that can lead to significant disputes over extensions of time and financial compensation.

The Society of Construction Law (SCL) Delay and Disruption Protocol (2nd Edition, 2017) stands as a beacon of guidance in this often-murky area. While not a legally binding document in itself, it’s widely respected and often referenced by courts and tribunals as best practice for resolving delay and disruption claims.

Let’s dive deep into what the SCL Protocol says about concurrent delay, particularly when the employer is a contributing factor, and how this impacts a contractor’s entitlements.

What is Concurrent Delay, Really? The SCL’s Refined View

Before the SCL Protocol, “concurrent delay” was a term thrown around with varying interpretations. The Protocol, however, offers a much-needed clarification, distinguishing between “true” concurrency and delays with “concurrent effects.” This distinction is crucial for understanding entitlements.

  • True Concurrent Delay (Rare Beast!): Imagine two separate, independent events. Event A is an Employer Risk Event – perhaps the client failed to provide approved drawings on time. Event B is a Contractor Risk Event – the contractor suffered a major equipment breakdown. If both of these events occur simultaneously and each independently causes delay to the critical path of the project, then you have true concurrent delay. The SCL Protocol acknowledges this as genuinely rare. Why? Because in most projects, delays tend to have ripple effects rather than perfectly synchronized, independent origins.
    • External Perspective (FIDIC): While the SCL Protocol offers a detailed definition, it’s worth noting that international contract forms like FIDIC (Fédération Internationale Des Ingénieurs-Conseils) often deal with concurrent delay through a “but for” test – essentially asking if the contractor would have been delayed anyway by their own events, even without the employer’s delay. This can sometimes lead to different outcomes than the SCL’s approach.
  • Delays with Concurrent Effects (The Common Scenario): This is where most “concurrent delay” scenarios actually fall. Here, an Employer Risk Event might happen, and then later, a Contractor Risk Event occurs, or vice-versa. However, at some point, their effects on the critical path overlap. The key here is that both events, irrespective of their start dates, become critical path delays during the same period.
    • Example: The employer delays providing access to a work area for two weeks (Employer Risk). Later, due to poor planning, the contractor runs into a labor shortage for three weeks, impacting the same critical path activities that were already pushed back by the access delay (Contractor Risk). For a period, both delays effectively impact the same critical path.

The SCL Protocol emphasizes that for a delay to be truly “concurrent” or have “concurrent effects” in a way that impacts entitlements, both delay events must be on the critical path to completion. A delay to a non-critical activity, even if occurring at the same time as a critical path employer delay, does not constitute concurrency in the context of EOT or loss and expense.

Entitlements in the Face of Concurrent Employer Delay: Time and Money

This is where the rubber meets the road. How do you allocate responsibility and adjust the contract when the employer is a cause of delay during a period of concurrency? The SCL Protocol offers clear guidance, treating extensions of time (EOT) and financial compensation (loss and expense) differently.

1. Entitlement to Extension of Time (EOT): The “Prevention Principle” Reigns Supreme

 

When an Employer Delay to Completion occurs concurrently with a Contractor Delay to Completion, the SCL Protocol generally advocates for the contractor to receive a full Extension of Time for the entire period of the Employer Delay.

  • The Rationale: The Prevention Principle. This principle, a cornerstone of English contract law, dictates that an employer cannot benefit from their own breach of contract or act of prevention. If the employer’s actions (or inactions) contribute to the project being delayed, they cannot then hold the contractor liable for not finishing on time.
  • No Apportionment for EOT: Crucially, the SCL Protocol states that the contractor’s own concurrent delay should not reduce the amount of EOT granted for the employer-caused delay. If the employer caused a critical delay, the contractor gets that time back, irrespective of their own concurrent delay.
    • Clarification (Scottish Law): While the SCL Protocol is broadly accepted in the UK, it’s worth noting that in Scottish law, the “apportionment” approach (where EOT might be split if delays are truly concurrent) has sometimes been favored by courts. This highlights the importance of the governing law of the contract. However, the SCL Protocol’s strength lies in its practical, common-sense approach to fairness.
  • Practical Impact: This means if a project is delayed by 30 days due to the employer’s late design information, and during those 30 days, the contractor also experiences a 15-day delay due to their own poor planning on a critical path activity, the contractor would still likely receive a 30-day EOT. The employer’s delay set back the contractual completion date by 30 days, and the contractor should not be penalized for that.

2. Entitlement to Compensation (Loss and Expense): The Cost Conundrum

While the SCL Protocol is generous with EOT during concurrent delay caused by the employer, it takes a more stringent approach to financial compensation (prolongation costs, or “loss and expense”).

  • No Automatic Compensation: The Protocol advises that the contractor is not automatically entitled to recover additional costs during a period of concurrent delay where both employer and contractor delays are critical.
  • The Burden of Proof: For compensation, the contractor must demonstrate that they incurred additional costs solely due to the Employer Delay that they would not have incurred anyway due to their own concurrent delay.
  • Separating Costs: This often requires the contractor to meticulously separate and prove which costs were directly caused by the employer’s delay. If the contractor would have incurred certain overheads or site establishment costs anyway because their own delay would have kept them on site for that period, then they cannot claim those specific costs from the employer.
    • Example: Following the previous example (30-day employer delay, 15-day contractor delay within that period), the contractor gets a 30-day EOT. However, for loss and expense, they would need to prove which, if any, of their additional site overheads or prolongation costs were exclusively due to the employer’s 30-day delay, and not to the 15-day period where their own delay would have kept them on site regardless. This can be incredibly difficult to prove in practice.
  • Why the Difference? The rationale is that while the employer should not prevent the contractor from completing on time (hence the EOT), the employer also shouldn’t pay for the contractor’s inefficiency or delays that would have occurred regardless.

Beyond the Definitions: Practical Application and Best Practices

 

The SCL Protocol isn’t just about definitions; it’s about practical application. Here are some key takeaways for all parties involved:

  1. Contemporaneous Records are King: The ability to prove delay and its causes hinges entirely on excellent, up-to-date project records. Daily diaries, meeting minutes, progress photographs, resource allocation sheets, and updated programmes are invaluable.
  2. Regular Programme Updates: A well-maintained and regularly updated project programme (or schedule) is critical. It allows for a clear, contemporaneous assessment of the critical path and how various events are impacting it.
  3. Proactive Communication: Early identification and communication of potential delays, whether by the employer or the contractor, can help mitigate their impact and facilitate resolution.
  4. Expert Delay Analysis: In complex cases, engaging a specialist delay analyst who understands the SCL Protocol and various methodologies is often essential. They can conduct a forensic analysis of the project programme and records to determine causality and concurrency.
  5. Contractual Clarity: While the SCL Protocol provides guidance, the contract itself remains paramount. Parties can choose to adopt alternative approaches to concurrent delay within their contract clauses. Always refer to the specific terms of your agreement.

Conclusion

 

The SCL Delay and Disruption Protocol provides a clear, rational, and widely accepted framework for navigating the treacherous waters of concurrent delay. By distinguishing between true concurrency and delays with concurrent effects, and by taking a nuanced approach to EOT versus financial compensation, it aims to achieve a fair outcome that respects the prevention principle while also holding contractors accountable for their own performance.

Understanding and applying the SCL Protocol’s principles can significantly reduce disputes, foster clearer communication, and ultimately contribute to the successful delivery of construction projects, even when the inevitable delays occur.


Construction Law, Contract Administration

Navigating the Tensions: A Guide to Mediation in Construction Disputes

Construction projects are inherently complex, often fraught with variables that can lead to disagreements, claims, and disputes. When a conflict arises, it can be costly in terms of time, money, and professional relationships. While a traditional approach might be to head straight to litigation, it is often more effective to leverage alternative dispute resolution (ADR) methods like negotiation and mediation. The key to success lies in understanding and managing three core tensions that exist in every dispute.

 

1. The Tension Between Creating Value and Distributing Value

In any dispute, there are two primary objectives: to create a larger “pie” of value that all parties can share, and to claim the largest possible slice of the existing pie for yourself.

• In a construction dispute, “creating value” means looking for a solution that benefits all parties beyond a simple financial settlement. This could involve agreeing to future collaboration, sharing a technical solution, or adjusting a project schedule to mitigate further costs for everyone.

• “Distributing value” is the more traditional, combative approach—arguing over who is owed what, based on the contract terms and legal positions. A successful negotiation or mediation requires parties to move beyond a purely distributive mindset. By focusing on creating value, such as a solution that keeps the project on track or preserves a long-term business relationship, parties can often achieve a better outcome than they would through a legal battle.

2. The Tension Between Empathy and Assertiveness

Effective dispute resolution requires a delicate balance between understanding the other side’s perspective and confidently advocating for your own.

• Empathy is about stepping into the other party’s shoes to understand their motivations, constraints, and fears. For a contractor, this might mean understanding the client’s financial pressures or the project manager’s need to meet a strict deadline.

• Assertiveness is about clearly and firmly articulating your position, rights, and interests. In construction, this involves knowing the contract language inside and out and being prepared to present a strong case for your claims.

Failing to manage this tension can derail a resolution. Too much assertiveness without empathy can lead to a stalemate, while too much empathy can result in a disadvantageous settlement. The best approach is to be strong on your interests, but soft on the people.

3. The Tension Between Principals and Agents

This tension highlights the conflict between the direct stakeholders (the principals—e.g., the company owner or client) and their representatives (the agents—e.g., project managers, superintendent, legal counsel).

• In a construction dispute, the agents are often the ones in the negotiation room, but they are not the ones who will ultimately live with the consequences of the resolution. Their incentives might be different from the principals’. A lawyer might be incentivized to pursue a case to trial, while a company owner might simply want the dispute to go away.

• Disputes often become more difficult to solve when the principals are not present or involved in the process. It is crucial for agents to have a clear understanding of their principals’ true interests and to ensure that a resolution aligns with those goals. The most successful mediations often include direct involvement from the decision-makers on both sides.

By keeping these three tensions in mind, parties involved in construction disputes can move beyond positional bargaining and work toward a collaborative solution that saves time, money, and most importantly, preserves critical business relationships.

Watch this related video:

: https://youtu.be/fS0T-Bbq5tU?si=xqL1B3vyIGovvHIg

Construction Law, Contract Administration

The Crucial Choice: One or Three Decision Makers in Construction Disputes

A fundamental question often arises at the heart of dispute resolution planning: should a dispute be decided by a single individual or a multi-member tribunal? This choice carries profound implications for speed, cost, expertise, and the ultimate robustness of the decision. This post delves into the arguments for each approach across various dispute resolution mechanisms, offering insights to inform this critical decision.

Construction Law, Contract Administration

Dispute Boards in Construction: Enforcement and Governing Law

Construction projects are complex undertakings, breeding grounds for disagreements that can escalate into costly, project-derailing disputes. For decades, the industry has sought better ways to resolve conflicts without resorting to lengthy arbitration or litigation. Enter the Dispute Board (DB), a project-based, real-time resolution mechanism designed to keep projects moving and relationships intact.

However, the power of a Dispute Board decision is not absolute. Its real-world teeth depend heavily on a crucial, often overlooked factor: the governing law of the contract. This article dives into the world of Dispute Boards, exploring how they function, how their decisions are enforced, and how the choice of jurisdiction can make or break their effectiveness, especially when compared to the statutory adjudication process.

Construction Industry, Construction Law, Contract Administration

The Critical Edge: Why Early Warning Notices Matter in FIDIC 2017

Unforeseen events and potential issues are almost inevitable in construction and infrastructure projects. How these challenges are identified, communicated, and addressed can significantly impact a project’s success, cost, and timeline. The FIDIC 2017 suite of contracts places a strong emphasis on proactive risk management and dispute avoidance, with the Early Warning Notice (EWN), specifically under Sub-Clause 8.4 [Advance Warning], being a cornerstone of this philosophy.

This post dives into the rationale and utility of Early Warning Notices under FIDIC 2017, exploring what happens if these provisions are not complied with, and outlining the responsibilities of all parties when such a notice is issued. …

Construction Industry, Construction Law, Contract Administration, Statutory Adjudication

Beyond Battles: How Dispute Boards Transform Construction Conflict into Collaboration

In the complex world of construction and large-scale infrastructure projects, effective dispute resolution is paramount to keeping ventures on track and budgets intact. While traditional methods like litigation and arbitration have their place, the rise of Dispute Boards (DBs) offers a proactive and often more efficient alternative. These independent bodies aim not just to resolve disputes, but, crucially, to manage and even prevent them from escalating, acting as an integral part of project delivery. …

Construction Law, Contract Administration, Security of Payment, Statutory Adjudication

Governing Law in Contracts: Navigating the Nuances of Jurisdiction and Practicalities

The seemingly straightforward governing law clause in any contract holds immense power, acting as the legal compass that guides the interpretation and enforcement of an agreement. While its fundamental purpose—to specify which legal system will apply in a dispute—remains constant, its practical application, particularly in dispute resolution forums like adjudication and arbitration, presents a fascinating array of challenges and jurisdictional distinctions. This post demonstrates how governing law truly operates across different legal systems. …

Construction Industry, Construction Law, Contract Administration

The Challenging Role of the Engineer/CA/PM in Construction Dispute Resolution

Disputes are an inevitable byproduct of complex projects, involving multiple parties, intricate contracts, and high stakes. At the heart of managing these conflicts, often with a heavy and unenviable burden, stands a key figure: the Engineer, Contract Administrator (CA), or Project Manager (PM).

Their role, as defined by various standard forms of contract, is often multifaceted, requiring them to be simultaneously technical experts, project leaders, financial custodians, and, crucially, initial dispute resolvers. It’s a tightrope walk where impartiality is expected, but practical realities often tug them towards one side. …

Scroll to Top