Navigating the Adjudication Process under the Building and Construction Industry Security of Payment Act 1999 (NSW)

By Dr Samer Skaik

The adjudication process, governed by the Building and Construction Industry Security of Payment Act 1999 (NSW), plays a crucial role in ensuring the speedy resolution of payment disputes within the construction industry. Let’s delve into the intricate details of this process and the key considerations for both claimants and respondents:

Initiating the Adjudication Application

  • Selection of Authorising Authority: The claimant has the discretion to choose an Authorising Nominating Authority (ANA) to nominate an adjudicator, raising concerns within the industry about the potential for bias in the appointment process.
  • Timely Application: The adjudication application must be made within specific time frames, either within 10 business days after receiving the payment schedule or within 20 business days after the due date for payment if any part of the scheduled amount remains unpaid.

Respondent’s Rights and Obligations

  • Adjudication Response: The respondent has the right to serve an ‘adjudication response’ within specific time frames, provided that a payment schedule has been served. The response must adhere to the limitations set by the SOP Act, disallowing the raising of new reasons beyond those mentioned in the payment schedule.
  • Potential Challenges: The SOP Act’s provisions may lead to what is referred to as ‘ambush claims,’ where the claimant has ample time to prepare a comprehensive payment claim, leaving the respondent with limited time to respond effectively.

Adjudicator’s Acceptance and Determination

  • ANA Referral: If the chosen ANA refers an adjudication application to an adjudicator, the adjudicator may accept the application and must serve a notice of acceptance on the parties within a specified time frame.
  • Expedited Determination: Upon acceptance, the adjudicator is obliged to determine the application expeditiously, typically within 10 business days after notifying the parties, or within an agreed-upon extended time frame.

Enforcement of Adjudicated Amount

  • Payment Obligations: The respondent must pay the adjudicated amount within five business days. Failure to do so enables the claimant to request an adjudication certificate from the ANA and serve notice on the respondent, ultimately allowing the adjudication certificate to be filed as a judgment for a debt in court.

Legal Implications and Criticisms

  • Jurisdictional Errors: Adjudicators must operate within the boundaries of their statutory powers to avoid invalidating the adjudication determination.
  • Complexity and Criticisms: The statutory mechanism’s ‘one size fits all’ approach has faced criticism for its limitations in handling larger and more complex payment claims, potentially impacting the quality of determinations.

Ensuring Fairness and Efficiency

By understanding and navigating the intricacies of the adjudication process outlined in the SOP Act, both claimants and respondents can work towards fair and efficient resolution of payment disputes within the construction industry. Compliance with statutory timelines and procedural fairness ensures the integrity of the process, ultimately contributing to the industry’s professionalism and financial stability.

In conclusion, the adjudication process under the Building and Construction Industry Security of Payment Act 1999 (NSW) serves as a fundamental mechanism for resolving payment disputes in the construction industry. By adhering to statutory requirements and procedural fairness, construction stakeholders can ensure transparent and efficient resolution of payment claims, promoting trust and stability within the industry.