The ins and outs of ‘suspension of the works’ under construction contracts

by Paul Taylor

Having considered the process of termination of construction contracts, the equally important subject of suspension of the works on a construction project should also be considered.

Suspension is perceived as slightly less draconian because the intention is usually to only invoke a temporary situation, where it is envisaged that the works will later be resumed. However, despite being entirely separate rights, suspension and termination are often linked because the former may ultimately lead to the latter.

Rights entitling one party to suspend the works can be found under the local law, and invariably under the contract between the parties.

In the UAE, the Civil Code allows a party to a contract to suspend works. For example, Article 247 states: ‘In contracts binding upon both parties, if the mutual obligations are due for performance, each of the parties may refuse to perform his obligation if the other contracting party does not perform that which he is obliged to do.’

The extent to which such provisions may or may not be successfully relied upon would depend on the particular facts before the court or arbitration tribunal, and it is therefore common for the parties to set out their express intentions and agreements regarding the right to suspend within the construction contract itself.

The widely used FIDIC Red Book (4th Edition) 1987 provides a number of entitlements to suspend. For example, where there is default by the employer, the contractor may suspend upon giving written notice to the employer (copied to the engineer) for the reasons set out under clause 69.4. These include failure by the employer to pay the amount due under any certificate within the timeframe allowed for. Any delay or costs incurred by the contractor in suspending under this provision shall entitle the contractor to an extension of time and those additional costs. The works are to be resumed under clause 69.5 once payment of the amount due is made.

The employer’s rights to suspend the works under this form of contract arise under clause 40.1 and result from an engineer’s instruction. Suspension in this case can be ‘for such time and in such manner as the engineer may consider necessary’. And again, time and costs should be evaluated and awarded by the engineer in such circumstances.

Permission to resume the works under clause 40.3 should be given by the engineer within 84 days from the date of suspension. If it is not, then various additional rights may accrue to the contractor, including the right to elect to treat the suspension as an omission (provided it only affects part of the works), or treat the ongoing suspension as a grounds for termination under clause 69.1. This is subject, as one might expect, to the reason for the suspension not being due to the default or breach of contract of the contractor in the first place.

The more recent 1999 FIDIC Red Book, under clause 16.1, grants rights to the contractor in the event of a default by the employer in paying amounts due under a certificate, and for failure to issue a payment certificate in the first place, among other things.

In addition, clause 8.8 provides the right to the engineer to issue a suspension notice in relation to all or part of the works and similar rights to extension of time and additional cost are granted to the contractor, provided of course that the cause is not the responsibility of the contractor.

From a practical perspective when considering a suspension (whatever the reason might be), it is important to:

• Ensure the events that you are seeking to rely on do fall within the parameters of the suspension provisions;

• Take note of and comply with the required notice periods;

• Ensure the notice complies with the contractual requirements such as ‘being in writing’ and ‘served at the correct address for service under the contract’;

• Ensure adequate and detailed records are maintained to support the events leading up to and invoking the suspension;

• Ensure adequate records of delay and additional costs are maintained and submitted in accordance with the contractual provisions for such claims.

As with termination, care and coordination is required in any suspension scenario, but when correctly implemented, suspension can in fact be an invaluable mechanism within the construction contract.

Construction week

  1. We are a specialist subcontractor for curtain walling. Our management has entered into a lumpsum contract and deem it is not commercially viable for us to perform in this project which is worth QR 14.2 Million. The contract was signed in 01 Nov 2009 and we want to cancel the contract. Completion date is 30 Aug 2010. Our client seems to have financial issues and we want to be out. There was no provision in the contract with regards our side mentioning our right to cancel our services. What would be the likely consequences of this and how are we going to get way with our action.

    thanks

    1. I assume that there is reference to standard conditions of Contract which refer to FIDIC 1999. If so, as per clause 2.4, the Employer is obliged to provide you the reasonable evidence of finalical arrangements made for the Project, within 28 days of request so made by the Contractor.

      I suggest to serve a notice to the employer to provide you the above details and, since you know that the employer has financial difficulty, he may not be able to provide you such detail. After that, serve a notice for breach of contract terms and approach the court for termination of the contract.

      This is one way you can come out of the project which is otherwise burdonsome for yoru organisation.

      Regards

      Kishan Solanki

  2. hi,
    A GOOD NOTE.I HAVE JUST ONE QUERRY.CAN CONTRACTOR BE PAID
    FOR WORK DONE PRIOR TO SUSPENTION DURING SUSPENSION PERIOD AS AN IPC IF CONTRACTOR IS NOT AT DEFAULT?

    1. It depends on the conditions of contract you are referring to. Kindly refer to relevant suspension clause. usually, the interim payment for works done shall be processed without any delay.

      Regards.

Discover more from CMGuide

Subscribe now to keep reading and get access to the full archive.

Continue Reading

Scroll to Top