Construction Law

Construction Law, Contract Administration

Front end advice

Despite the harsh lessons learnt over the latter part of 2009 and first quarter of 2010 it is still patently obvious that parties to contracts are falling into a number of age old pitfalls, many of whom are convinced that they have no other viable choice but to accept top-down back-to-back arrangements and in some cases a scramble of documents that barely resemble a contract at all.

There is still an overwhelming market tendency to order mobilisation and commence work on the back of a very brief Letter of Intent (LOI), particularly if the commissioned works are minor works or low value. This is a particularly high risk practice. …

Construction Law, Contract Administration, Dispute Boards

Dispute boards: the missing link?

   Leonora Riesenburg.

After the Dispute Review Board (DRB) Foundation and Society of Construction Law (Gulf) met to discuss dispute boards and their function in the local market, many praised the ‘checks and balances’ proffered by the mechanism.

The rationale behind the dispute board is simple. The DRB provides a non-binding recommendation to contracting parties that have appointed a board of three independent experts, intended to comb out difficulties either prior to the offset of, or in answer to, a problem.

A similar principle applies to the Dispute Adjudication Board (DAB), save that the DAB’s decision has interim-binding force.
Dispute boards have been given tour de force by the active support of the Dispute Board Federation, the Dispute Resolution Board Foundation, ICC, and standard-form contract authorities including the International Federation of Consulting Engineers (FIDIC).

This form of independent regulation has had a warm welcome in the West. Interestingly though, collaboration contracts such as NEC have been tested in territory, most notably by Abu Dhabi’s Aldar Properties in the early phases of Al Raha Beach Development, and failed to take flight.

Creating valuable opportunities for periodic review is fine in theory. In practice, however, it is rare that two parties’ agendas will be aligned in such a way as to capitalise on the opportunity.

Competing interests are a particular concern when more than two parties are involved. Returning control to the employer and the contractor is only worth the paper it is written on to the extent that the employer and contractor play ball.

In the case of long-term appointments, a day rate, allowances and disbursements customarily need to be shouldered for all three board members, over the course of the life of the project, however lengthy. The cost implications can be staggering.

The fact of the matter is that employers will never want to pay above a budgeted figure for the contracted services, and service providers will be bent to do their utmost to secure their minimum margin.

The equation only ever balances if the margin for error is not eroded. Commercial reality dictates that errors are made and a price tag is attached to each of them. It is the allocation of these risk events, and in turn its cost, that is the bone of contention among contracting parties.

The effectiveness of an independent administration, in the form of dispute boards, in the context of this tension, is questioned.

The UAE has been slow to apply FIDIC 1999, calling for the appointment of a DAB as part of its dispute process. If and when adopted, the standard conditions are often heavily modified and reinstate the engineer’s traditional role as a de facto ‘dispute manager’.

Further the language of contracts in territory is slow to entertain the admissibility of recommendations or resolutions in any subsequent arbitration or legal suit.

When legal fees are calculated on a percentage fee basis, irrespective of complexity, the mathematical exercise rapidly dwarfs the financial benefits attributed to the DB.

The Abu Dhabi Municipality has moved the markers further afield with its Municipality Construction Contract, essentially a heavily modified form of the 1999 FIDIC Contract for Construction, by making it mandatory for a ‘standing’ DAB to be appointed once a dispute has arisen.

A ‘standing’ DAB is in effect a half-way house. Where the Municipality Contract gives on one hand, it takes on the other: the engineer’s role in dispute resolution is re-assigned to the employer.

One would not need to go into any further detail to entertain that dispute boards, particularly given their limited application in territory, are not a means to an end.

There is no real replacement for proper internal administration coupled with continuous sound legal counsel and guidance to complement to the day-to-day workings of commerce.

CW

Construction Law, Contract Administration

Tales of the Unexpected: Where Liability Lurks Unseen

by Melanie Grimmitt

Uncertainty in the Application of UAE Laws

The UAE legal system is a civil code system based on both Islamic and civil code principles. Any contract subject to UAE law must comply with the UAE Constitution, Federal and local Emirate laws, Islamic Shari’a and custom and practice.

There are challenges in deciding how the law of the UAE will be applied in any particular case. This is due to a number of factors. The UAE legal system is still very much in its infancy, the collision of French – via Egypt and other Middle Eastern countries – civil code principles and Islamic Shari’a principles, the lack of judicial precedent – previous decisions may be useful but do not create any binding or persuasive precedent to the court, and the difficulty of predicting which legal principles and/or custom and practice a judge will apply when reaching a decision. …

Construction Law, Contract Administration

Letters of Intent: Still Crazy After All These Years?

by Melanie Grimmitt

Reviewing the wealth of commentary on the use of letters of intent in construction contracts, one might speculate that at the time the pyramids were being built some well-intentioned Egyptian lawyer was earnestly hammering out hieroglyphics warning his contemporaries of the potentially dire consequences of commencing construction works without a concluded contract in place. Nevertheless, despite the plentiful guidance cautioning contractors against relying on letters of intent which has been produced by legal professionals in more modern times, a significant proportion of construction projects do, in fact, proceed on the basis of a letter of intent. This practice is particularly common within the UAE and the wider Gulf Region. …

Construction Law, Contract Administration

Record what happened, when it happened – the importance of ‘contemporary records’

by Sachin Kerur

A large part of the administration of a construction contract comprises a contractor seeking genuine contractual entitlements for additional time and costs and the determination and award or rejection of those claimed entitlements by the engineer/employer. As a result, contractor’s claims for extensions of time and additional costs are also often the subject of arbitral proceedings and litigation. …

Construction Law, Contract Administration

Liquidated Damages in PPP Transactions

by Melanie Grimmitt

One of the most interesting aspects of working in different jurisdictions is seeing how different regions approach the same issues in different ways – both legally and commercially. An example of this in the context of PPP transactions, is the differing approach taken in the UK and the Middle East in respect the inclusion of delay liquidated damages regimes in Project Agreements. …

Construction Law, Contract Administration

When is it safe to terminate under a contract?

by Vincent Connor

Volcanoes – we have rather a lot of them in Asia, but even we’ve been obsessing about the infamous Icelandic one, this week. Though 6000 or more miles away from the action, Japanese car manufacturers relying on components from Ireland and Korean mobile phone suppliers ready to send their wireless wares to a waiting world, have been among those frustrated as the volcanic ash cloud has choked airfreight routes. Which got me thinking…not so much about force majeure (I’ll leave that to my holidaying partners examining their insurance documents to seek support for their compensation claims!) but about the options a contracting party faces when the party with whom he’s entered into an agreement has breached a material provision (say, a delivery date): should he accept that party’s repudiation and sue for damages or simply terminate it in accordance with the procedure provided for in the agreement? …

Construction Law

A Growing Trend in French Construction Law? The Recognition of Mandatory Rules by the Court of Cassation

by Joanne Clarke

In a judgment dated February 25, 2009 (Cour de cassation, civ. 3, 25 February 2009, No. P07-20.096), the Court of cassation, the highest court in the French judiciary, confirmed its previous decisions (Cour de cassation, chambre mixte, 30 November 2007, No. 06-14.006; Cour de cassation, 3e civ., 30 January 2008, No. 06-14.641) according to which certain provisions of the French Law on Subcontracting dated December 31, 1975 are mandatory, and as such are to be applied even when French law is not the governing law chosen by the parties to the contract. …

Construction Law, Contract Administration

How subcontractors can get paid

One of the critical but not “headline making” aspects of the downturn in the construction industry is that many subcontractors are having difficulty getting paid on projects and meeting their own debts as they fall due.

The subcontractor is usually dependent on the contractor being paid under the main contract. One often sees a “pay when paid” clause in subcontract which essentially means that the subcontractor will not be paid by the contractor until the contractor has been paid for the subcontractor’s work by the employer. This necessarily involves even in the best case scenario a longer credit period to the contractor than the contractor in turn gives to the employer. The subcontractor generally has little input in to the certification process by the employer’s advisor prior to him or her approving an invoice in favour of the contractor. …

Construction Law, Contract Administration

FIDIC’S FOUR NEW STANDARD FORMS OF CONTRACT: Risks, Force Majeure and Termination

 By Christopher R. Seppala

I propose briefly to discuss five topics in the three new Books for major works (the new Construction Contract, the Plant Contract and the EPC Contract), as follows:

 (1) Contractor’s risk and “Employer’s Risks”,

(2) Indemnities,

(3) Limitation of Liability,

(4) The New Force Majeure Clause, and

(5) Grounds and Procedure for Termination of the Contract by the Employer and the Contractor. …

Construction Law, Contract Administration

Making Demands on Advance Payment Guarantees and Performance Bonds: The Test to Secure Summary Judgment on a Claim before the English Court

by Karen Gough

We are in the midst of a world-wide recession. So, in times when contractors’ liquidity and therefore their very survival is more at risk than usual, and employers are more than usually jittery about the ability of contractors to complete works, a recent decision on a claim to enforce an advance payment guarantee and a performance bonds is of particular interest to construction law practitioners. …