The Delays We Cause Ourselves: Land, Permits and Utilities on Public Infrastructure Projects
By Dr Samer Skaik
On a large proportion of internationally financed infrastructure projects, the single biggest source of delay is not the contractor. It is the employer’s own inability to hand over the site.
Land that has not been acquired. Households that have not been resettled. A right of way that runs through three private holdings and a cemetery. Electricity poles, water mains and fibre that belong to state-owned utilities with no contractual relationship to the project and no particular urgency about it. An environmental clearance sitting with a regulator that answers to a different minister. Building permits from a municipality that was not consulted during design.
None of this appears in the contractor’s risk register, because none of it was ever the contractor’s to carry. Under the standard forms including FIDIC these are employer obligations, squarely and unambiguously. The contract requires the employer to give the contractor the right of access to and possession of the site, and where it fails to do so within the time required, the contractor is entitled to time and money.
Everyone involved knows this. And yet I have read many project documents in which the delay is described in the passive voice — access was not available, the site could not be handed over — as though it happened weather-like, to nobody in particular. …