Techniques to Get back on Budget

Implement “Zero Tolerance” Scope Change Management

This technique can be applied to help remedy a project that is either over deadline or over budget. Many projects begin to trend over their budget because they are doing more work than they originally committed to as a result of poor scope change management. If you are at risk of missing your budget, the project manager must work with the client and team members to ensure that absolutely no unplanned work is being requested or worked on – even if it is just one hour – unless formal scope change management is invoked. To repeat – this does not mean that there can be no more scope change requests. It simply means that EVERY scope change request must go through scope change management (which should be happening anyway). All other energy should go into cutting costs and completing only the core work that was agreed to.

Use Budget Contingency (If You Have it)

If you are fortunate, your initial budget included a contingency to account for the uncertainty and risk associated with your estimate. For instance, it would not be unusual for a project to include a 10% contingency. The contingency is separate from the project budget. If you can complete the project within your initial budget, the contingency should all be returned to the company. If you find that your over-budget situation is caused by activities that are costing more than estimated, the contingency budget can be tapped. When you do this, make sure your sponsor and key stakeholders know so that you manage expectations about the amount of contingency funding remaining.

Improve Processes

There may be cost overruns caused by inefficient internal processes. Get team member feedback and look for ways that are within your team’s internal control to streamline processes. If there are cost implications caused by external processes, try to negotiate changes to the processes on a going forward, or at least a temporary basis.

This is a good technique for longer projects since you have a chance to optimize your project processes, see the results and optimize some more. However, it may not make sense for smaller projects. It is hard to do much process improvement on a 30 day project. By the time you would want to make any process improvements the project would probably be over.

Set up More Detailed Cost Accounts

Just as it is difficult to manage activities that have a long duration, it can also be difficult to manage the budget if the funding is all in one place. In both cases, the difficulty arises because you have a hard time understanding where you are at any given time. One technique to provide more budget control is through the use of more detailed cost accounts.

Cost accounts are ways to allocate funding for your project so that you have more precise control. Instead of having one large budget with all of your costs, you can separate your overall budget into lower level cost accounts. For example, you could set up a cost account for each phase of your project. You could also set up a cost account for each deliverable. Since these budgets are now allocated at the lower level, you are in a position to know much earlier if you have budget problems.

For instance, you could set up a cost account for the Analysis Phase of a project. When the Analysis Phase is completed you could compare your actual spending with the budget for this phase. If you are over your budget, that would give you an indication that you are trending overbudget for your entire project. If you do not have the budget broken down into these smaller cost accounts, it may not have been obvious how much you expected to spend on the Analysis Phase and how much you actually did spend.

tenstep

  1. This is what the Quantity Surveyor provides: the Cost Plan which is used to control the project cost from the very beginning even before tender is issued. Every change, whether it results in an increase or decresase in the project cost, is costed before commitment.