Contract Administration

Construction Law, Contract Administration

FIDIC’s International Contract Users’ conference – CMguide readers get a 10% saving…

Now in its 25th year, FIDIC’s International Contract Users conference is indisputably the leading international forum for those wishing to make the most of the FIDIC suite of contracts.

Remain ahead of the field with exclusive, insider insights from the very people responsible for drafting and updating the contracts. …

Construction Law, Contract Administration

Liquidated Damages for Construction Delays

Liquidated Damages is defined as “a sum which a party to a contract agrees to pay or a deposit which he agrees to forfeit if he breaks some promise and which, having been arrived at by a good faith effort to estimate in advance the actual damage which would probably ensue the breach, are legally recoverable or retainable as agreed damages if the breach occurs.” …

Contract Administration

Force majeure – the devil is in the detail

By Ruth Wilkinson

Key Points:
• A force majeure clause normally excuses one (or both) parties from performance of the contract in some way on the occurrence of a specified event or events beyond their control

• In English law what constitutes force majeure varies widely between contracts

• Most construction contracts define what is meant by force majeure and prescribe the time and cost consequences, as well as what happens to the contract going forward

• The courts have taken a narrow approach to construction of force majeure clauses, requiring that obligations have actually become impossible to perform, not merely more difficult or less profitable

The origin of the doctrine of force majeure is the French Civil Code. It has been used as a defence to a claim for breach of contract as in effect it relieves a party of performance because of some ‘act of God ’ or unavoidable catastrophe. A force majeure event may be relied upon if it has made performance of the contract impossible, was unforeseeable and was unavoidable in consequence and effect.

But in English law it is not so simple. The term ‘force majeure’ is not a legal term of art. Chitty describes the normal understanding of the purpose of a force majeure clause as follows:

‘
[a force majeure clause is] normally used to describe a contractual term by which one (or both) of the parties is

entitled to cancel the contract or is excused from performance of the contract in whole or in part, or is entitled to suspend performance or to claim an extension of time for performance, upon the happening of a specified event or events beyond his control.’

Typical force majeure events would include war, riot, civil commotion, strike and natural catastrophes (such as earthquakes and hurricanes) but would not include bad weather, football matches, a funeral or an act, negligence or omission by the party seeking to be excused.

The concept of force majeure cannot be relied upon as a defence unless and to the extent that the contract so provides, or if it is implied as a term. Construction contracts will usually define what is meant by force majeure and the consequences. The precise terms and effect of such clauses can vary widely.

As the leading authority on force majeure in English law (the judgment of McCardie J. in Lebeaupin v Crispin [1920] 2 KB 714) states, the precise ambit of the term will depend on the context in which it is used:

‘A force majeure clause should be construed in each case with a close attention to the words which precede or follow it, and with a due regard to the nature and general terms of the contract. The effect of the clause may vary with each instrument.’

It is common to see force majeure defined by a list of events followed by a general sweep up provision. In Tandrin Aviation Holdings Ltd v Aero Toy Store LLC [2010] EWHC 40 (Comm) the defendant sought to justify its refusal to accept delivery of an aircraft on the basis that the alleged ‘unanticipated, unforeseeable and cataclysmic downward spiral of the world’s financial markets’ constituted ‘any other cause beyond the Seller ’s reasonable control’ as provided for in the force majeure clause of the contract. This, they said, postponed the time for the defendant to complete the purchase.

The judge rejected the argument. He held that this phrase had to be read in the context of the entire clause. Although the judge noted that the phrase ‘any other cause beyond the Seller’s reasonable control’ did not need to mirror the specific examples set out earlier in the definition, he pointed out that it was nonetheless telling that nothing in any of those specific examples was even remotely connected with economic downturn, market circumstances or the financing of the deal.

A force majeure clause may provide relief from liability when a party is prevented from carrying out his obligations or is unable to do so. However, a party seeking to rely on a clause which states that he is relieved of his obligations if he is prevented from carrying them out must show that performance has become physically or legally impossible, and not merely more difficult or unprofitable.

It is not unusual for contractors to claim that whilst performance of the contract is technically possible, it has become financially unviable, so much so, that it is economically impossible.

Generally, a change in economic or market circumstances affecting the profitability of a contract or the ease with which the parties’ obligations can be performed will not be regarded by the courts as constituting a force majeure event. This was the case in Tandrin above.

Thames Valley Power Ltd v Total Gas & Power Ltd [2006] 1 Lloyd ’s Rep 441 established:

‘… It does not at all follow that the supplier is entitled to rely upon an increase in the market price in comparison to the contract price as a force majeure circumstance … This conclusion is consistent with a line of cases, both on force majeure clauses

… to the effect that the fact that a contract has become expensive to perform, even dramatically more expensive, is not a ground to relieve a party on the grounds of force majeure …’

The burden of proof is on the party seeking to rely upon the force majeure clause. He must prove the occurrence of the event he is relying on and that he has been prevented, hindered or delayed (as the case may be) from performing the contract by reason of the event. Subject to the terms of the contract, he must also prove that the event in question was beyond his control and that there were no further steps he could have taken to avoid or mitigate the consequences: Channel Island Ferries Ltd v Sealink UK Ltd [1988] 1 Lloyd ’s Rep 323. In that case a clause that included ‘strikes beyond [its] control’ did not bite if the party seeking to rely on the clause could have settled the strikes by taking reasonable steps.

The standard form construction contracts deal with force majeure differently as illustrated by comparing NEC3, JCT 2011 and the FIDIC Red Book.

NEC3

The term force majeure is not used in NEC3, however cl 19.1 (Prevention) is the equivalent. Clause 19.1 states:

‘ If an event occurs which

• stops the Contractor completing the works or

• stops the Contractor completing the works by the date shown on the Accepted Programme,

and which

• neither Party could prevent and

• an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that

it would have been unreasonable for him to have allowed for it,

the Project Manager gives an instruction to the Contractor stating how he is to deal with the event’.

Such an event is a compensation event (cl 60.1(19)) and a ground upon which the employer may terminate (cl 91.7). Clause 91.7 requires that the event must stop the works completing by the date shown on the Accepted Programme and ‘is forecast to delay Completion by more than 13 weeks.’

The NEC3 Prevention clause is generally regarded as providing a more generous approach for the contractor than a typical force majeure clause, since it puts the onus on the employer to decide how such events should be dealt with and entitles the contractor to both time and money where such events arise. As many employers are uncomfortable with the prospect of considering whether an event is one which it would have been reasonable for a contractor to allow for, these provisions are often deleted by employers, with the result that the contractor may have no effective remedy in the event of force majeure.

JCT

The JCT form clause references are to JCT 2011 With Quantities which includes express reference to force majeure; but it is not defined, which gives rise to potential uncertainty about its scope. In the absence of such a definition Keating on Construction Contracts (9th edn, para 20-118) suggests that the court would follow Lebeaupin v Crispin when attempting to define what a force majeure event would include.

Force majeure is listed as a relevant event which entitles the contractor to an extension of time (cl 2.29.14). It is not identified as a relevant matter for the purposes of recovering loss and expense. It sits alongside other events which could ordinarily be considered as force majeure such as ‘exceptionally adverse weather conditions’ (cl 2.29.9), ‘civil commotion’ (cl 2.29.11), or ‘strike’ (cl 2.29.12).

It may also be a ground for termination (cl 8.11). Clause 8.11.1 provides that if before practical completion, the whole or substantially the whole of the uncompleted works is suspended for the period specified in the contract particulars by reason of various events including force majeure, then either party may give notice of termination.

FIDIC

Clause 19 of the Red Book states:

‘ In this Clause, “ ‘Force Majeure” means an exceptional event or circumstance:

a) which is beyond the Party’s control,

b) which such Party could not reasonably have provided against before entering into the Contract,

c) which, having arisen, such Party could not reasonably have avoided or overcome, and

d) which is not substantially attributable to the other Party.

Force majeure may include, but is not limited to, exceptional events or circumstances of the kind listed below, so long as conditions (a) to (d) above are satisfied:

i. war, hostilities (whether war be declared or not), invasion, act of foreign enemies,

ii. rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war,

iii. riot, commotion, disorder, strike or lockout by persons other than the Contractor ’s Personnel and other employees

of the Contractor and Sub-Contractors,

iv. munitions of war, explosive materials, ionising radiation or contamination by radio-activity, except as may be

attributable to the Contractor ’s use of such munitions, explosives, radiation or radio-activity, and

v. natural catastrophes such as earthquakes, hurricane, typhoon or volcanic activity.’

Read on their own, sub-clauses (a) to (d) could be seen as providing a broad definition of force majeure, however, in line with Lebeaupin v Crispin , reading these with the subsequent sub-clauses I to V may well limit the definition of force majeure.

Clause 19.4 provides that the Contractor can recover an extension of time and can on the occurrence of events I to IV recover cost subject to (in relation to I to IV) these occurring in the country in which the site is located. Clause 19.6 provides that either party may give notice of termination if the execution of substantially all the works is prevented for a continuous period of 84 days by reason of force majeure or for multiple periods totalling more than 140 days.

Summary

These are just examples of some of the standard forms’ treatment of force majeure. It makes sense to consider carefully at drafting stage what parties wish force majeure to look like – as always, it is about who bears the risk. The devil is, as they say, in the detail.

www.dundas-wilson.com

Construction Law, Contract Administration

Liquidated damages: who pays for losses?

 By KATIE LISZKA

THE use of liquidated damages provisions is widespread throughout the construction industry. Those operating in the industry locally are generally familiar with the underlying legal principles applying to such provisions, such as the fact that there are marked differences between the treatment of liquidated damages under the UAE law and English law. …

Contract Administration

Demystifying the Role of Engineer under FIDIC Forms

By Dr. Chandana Jayalath

The contractual ‘engineer’ could be anyone designated as the Engineer under the contract. As per clause 1 in any standard form, the engineer and his representatives (assistants and inspectors named under FIDIC versions to represent the engineer) are two different personalities. The engineer’s representative is appointed by the employer to perform the duties delegated under another clause (clause 3 under new forms). It is the engineer who shall notify such an assignment of duties and delegation of authority to the contractor in writing indicating the extent of authority to act as the engineer’s representative. …

Construction Law, Contract Administration

Delay and extensions of time in construction contracts

Delay – what is the common law position? Why is a completion date needed?
If no agreement is reached on the time within which a service must be performed, it only needs to be performed within a reasonable time. Whilst this may be workable in the context of, say, a contract for the delivery of a new washing machine, it is not satisfactory when applied to something as complex as a construction project. …

Construction Law, Contract Administration

Liquidated damages clauses in construction contracts

Most forms of building contract include a clause entitling the Client to a specified level of damages, referred to as “Liquidated Damages” or “Liquidated and Ascertained Damages” if the Contractor is late in handing over the building. LADs replace the Client’s common law right to damages for late completion with a contractual right to a pre-determined sum for the period of delay. …

Contract Administration

Turnkey Contracts

By Chris Wilcock
Managing complex disputes can be difficult. The recently-reported Australian case of Alstom v Yokogawa1 highlights how it can go horribly wrong. In March 2002, Alstom entered into a ‘turnkey’ contract with FPP as the owner. Alstom agreed to refurbish an ageing power station to meet a performance specification. The contract sum was AU$148m. There were staged completion requirements and significant delay damages. …

Construction Law, Contract Administration

Procurement in Abu Dhabi

By KATIE LISZKA and NAZLI OKUSLUK

ABU DHABI Law No 6 of 2008 (procurement law), which governs the procurement of materials, service contracts and works contracts in the Emirate of Abu Dhabi, aims to decentralise, modernise, simplify and facilitate procurement by government departments. It grants the Department of Finance the authority to issue a manual to execute the provisions of the law, pursuant to which the department issued the Purchases, Tenders and Bids Manual in 2008 (manual). This manual sets out provisions, policies and procedures in respect of tenders for purchasing materials, services contracts and executing works and bids, in addition to the terms and policies related to electronic tenders and purchases.ScopeWithout prejudice to the provisions of Law No 21 of 2006 regarding construction contracts and agreements in the field of civil works, the procurement law and the manual are in principle applicable to all government departments and agencies funded under the general budget of Abu Dhabi and apply to all contracts, except for the following:

(a) Direct employment contracts entered into between a government department and employees;

(b) Purchases by and contracts of the Abu Dhabi Police;

(c) Buildings leases provided to the employees of a government department; and

(d) Contracts entered into with other government entities.

In addition, the Executive Council of the Emirate of Abu Dhabi may, at its discretion, determine that the provisions of procurement law and the manual will not apply to a specific tender.

Types of tenders

The two main types of tender process are the general, which is a public tender, and the limited, which is a restricted tender.

• General tender: Designed for contracts exceeding Dh50,000 ($13,611), general tenders are based on three principles, namely, openness, equal opportunity and freedom of competition, and involve four main steps: announcement of tenders; evaluation of proposals; awarding contracts; and supplying goods or performing work.

General tenders can be either global or local. A global general tender is where invitations to tender are open to suppliers and contractors from within the country and abroad and advertised in the local as well as international media. A local general tender is where invitations are restricted to suppliers and contractors within the country and advertised in the local media only.

• Limited tender: Here, the invitation is given to a restricted number of registered suppliers and contractors selected by the relevant department. The minimum number of tenders for this process is three.

Such a tender may be international or local and is sometimes called the “selective tender” or the “tender from the list” as it is based on selecting certain suppliers or contractors from a register (see below) and inviting them participate. This process may be appropriate in circumstances where there are, for example, only a certain number of specialist suppliers.

Except for general advertising, all the rules and procedures for public tenders apply to limited tenders.

Pre-qualification

Registration is a pre-condition of doing business with government entities in Abu Dhabi and the procurement department of each government entity keeps a register of suppliers and contractors qualified to provide services and products to that government entity. If a bidder in a public tender is not on the register, it must fulfil the qualification conditions before the bids are opened.

Qualification standards

Qualification standards and conditions cover the following aspects:

(a) Legal, including the requirement for licences to practice the activity (from Planning and Economic Department, Chamber of Commerce and Industry, or any other entity);

(b) Commercial, including the relationship with licence agencies and previous transactions with the relevant government and other entities;

(c) Financial, including the financial position of the tenderer and arrangements and relationships with its banks and other financing sources;

(d) Technical, including that the tenderer has professional technicians and appropriate and sufficient equipment, workshops and warehouses; and

(e) Expertise, which can be evidenced by the successful completion of previous transactions.

Procedure

• Invitation to tender: The tendering government entity publishes an invitation to tender in newspapers, magazines and its official website (in case of public tenders) or sends the invitation directly to a specific number of suppliers or contractors (in case of restricted tenders) in order to get offers.

• Tender documents: These documents can be collected from the procurement department immediately after the invitation to tender is announced for a cash fee. They must be stamped and signed by the procurement department of the relevant government entity.

• Clarification meetings: In order to assist the bidders in preparing their bids, meetings may be held prior to submitting bids for the purpose of replying to any enquiries or questions. To ensure equal opportunity, the same information will be provided to all bidders. The manual strictly prohibits any information being provided to bidders by other means.

• Bid submission: Bids must be submitted in the required form to the envelopes opening committee, which comprises of at least three members with experience and competence in legal and financial aspects of the procurement.

A participant is permitted to submit more than one bid, provided that he shall provide for each bid a separate set of original tender documents. Submissions received after the deadline shall not be accepted.

• Bid security: For bids exceeding a value of Dh1 million ($272,238), the procurement department may decide that bid security is required.

• Reviewing bids: Once the bids are opened by the envelopes opening committee, they are delivered to the concerned technical division of the tendering government department to conduct a technical assessment. Bids accepted from a technical perspective shall be forwarded to the procurement department for financial evaluation in the case of procurement of materials, and in the case of procurement of services and works, to the relevant division.

• Notifying the successful bidder: The successful bidder will be notified of the acceptance of its bid by letter no later than a week from the date at which the procurement department approves the recommendations of the tenders and auctions committee. For unsuccessful bidders, envelopes will be returned along with a letter clarifying the reason for rejection.

• Performance bond: The successful bidder is required to submit a performance bond within 15 days from the date it is notified of the acceptance of its bid. The performance bond, to be provided before execution of the contract, is for between five and 10 per cent of the bid’s value. No interest will accrue on this bond.

If the successful bidder fails to provide the performance bond within the prescribed time period, the procurement department may call on the bid security and perform the subject of the tender in whole or in part on its behalf without taking any legal action and without prejudice to any of its legal rights.

• Contract execution: The successful bidder must sign the contract after being notified of the award and submitting the performance bond. If the successful bidder fails to sign the contract, without reasonable justification, within 15 days of being notified of the award, it shall be deemed to have withdrawn and the bid security can be called on.

Other provisions

Apart from tender procedure, the manual also contains information on internal procedures and regulates contract periods, penalty payments and dispute resolution, among other things.

• Internal procedures: The manual specifies in detail the relevant committees (such as the tenders and bids committee, and the envelopes opening committee) and officials (such as the officer in charge of contract management) who will be running the procurement process as well as their tasks and duties.

• Delay penalty: If there is a delay in completing the works within the specified time, a delay penalty will be imposed on the contractor, in accordance with the conditions of its contract. That penalty should not exceed 10 per cent of the total value of the contract.

• Claims and disputes: The relevant department must solve the contractual problems amicably by consent as far as possible. If these cannot be so resolved, the dispute shall be settled in accordance with the terms of the contract. If a dispute cannot be settled amicably, the parties have the right to go to the courts and may appeal to arbitration either under the terms of the original contract or by a separate agreement.

Gulf Construction Online

Scroll to Top