FIDIC

Construction Law, Contract Administration, Dispute Boards, Project Management

The Engineer Who Cannot Decide: Contract Administration Inside a Government Approval Chain

B Dr Samer Skaik

There is a moment in project meetings that anyone who works on public infrastructure will recognise.

A question is put to the engineer. It is a fair question, within the engineer’s remit, and the answer is not especially difficult. And before answering, the engineer glances at the employer’s representative sitting across the table.

It lasts less than a second and everybody in the room sees it. The contractor sees it and files it away. The engineer’s own team sees it. And what it communicates is that the person the contract designates as the impartial administrator of this contract is, in practice, checking.

I do not raise this to criticise the engineers involved, most of whom are experienced professionals in an impossible position. I raise it because it is a structural problem specific to public employers, the contract does not solve it, and it is the origin of a startling number of the disputes I see. …

Construction Law, Contract Administration, Project Management

The Suspension That Never Ends: The 84-Day Clock and the Choice at the End of It

By Dr Samer Skaik

Suspension is the most under-used and most abused provision in the FIDIC time clauses, and it manages to be both at once for the same reason: it looks like a neutral administrative step and it is not.

The power itself is broad. The Engineer may instruct the Contractor to suspend progress of part or all of the Works, and under the 1999 wording is not obliged to give a reason. The Contractor must then protect, store and secure whatever has been suspended. In exchange, where the suspension is not attributable to the Contractor, it is entitled to an extension of time and to its Cost, with the 2017 edition treating the profit element more generously than its predecessor.

That is the clause. What makes it interesting is what happens when a suspension stops being an event and becomes a condition. …

Construction Law, Contract Administration, Project Management

Telling a Contractor to Speed Up: The Instruction Employers Keep Getting Wrong

By Dr Samer Skaik

A project falls behind. The Employer becomes anxious. Somebody suggests that the Engineer should instruct the Contractor to accelerate, and a letter goes out.

What happens next depends entirely on a distinction that is rarely drawn at the time the letter is written, and the cost of getting it wrong runs in both directions. I have seen Employers believe they had purchased acceleration when they had bought nothing at all, and I have seen Contractors treat a routine progress instruction as a blank cheque and spend accordingly.

The provision at the centre of this is Sub-Clause 8.6 in the 1999 editions, renumbered 8.7 in 2017. It is worth being precise about what it does, because it is almost the opposite of what people assume. …

Construction Law, Contract Administration, Dispute Boards, Project Management

When the Banks moved onto FIDIC 2017: What Public Employers Inherited With the New Contract

By Dr Samer Skaik

A few years ago I sat in a workshop with the contract management team of a national roads agency. They were good at their jobs. Several of them had been administering donor-funded works contracts for well over a decade, and between them they had probably handled more claims than some law firms see in a generation.

About an hour in, one of the senior engineers said something that stopped the room. He said: we have been running this contract the way we ran the last four, and I am starting to think it is not the same contract.

He was right. It was not. …

Construction Law, Contract Administration, Dispute Boards, Project Management

The Programme Nobody Agreed To: Sub-Clause 8.3 and What Silence Actually Means

By Dr Samer Skaik

Ask three people on a FIDIC project what status the programme has, and you will usually get three answers.

The planner thinks it is a management tool. The contractor’s commercial manager thinks it is the baseline against which every delay claim will eventually be measured. And the Engineer, if pressed, will often say that it was never approved, which is a curious thing to say about a document the whole project has been working to for two years.

All three are partly right, and the confusion is not their fault. Sub-Clause 8.3 is one of the shortest provisions in the contract carrying one of the heaviest practical loads, and it does not answer the question everyone actually wants answered: is this thing binding? …

Construction Law, Contract Administration, Dispute Boards, Project Management

The First Four Weeks: How Public Infrastructure Employers Set a Project Up to Avoid Disputes

 

By Dr Samer Skaik

The call usually comes about eighteen months in.

Someone from an implementing agency, often a project manager who has inherited the file from a predecessor, explains that things have gone badly wrong. The ground turned out differently from the investigation report. The utility diversions never happened. The contractor has submitted a claim with a number in it large enough that it has now been seen by people several floors above the project office. And somewhere in the conversation comes the question I have learned to brace for: we think the contract requires us to have a dispute board — how quickly can one be set up? …

Contract Administration

Force majeure – the devil is in the detail

By Ruth Wilkinson

Key Points:
• A force majeure clause normally excuses one (or both) parties from performance of the contract in some way on the occurrence of a specified event or events beyond their control

• In English law what constitutes force majeure varies widely between contracts

• Most construction contracts define what is meant by force majeure and prescribe the time and cost consequences, as well as what happens to the contract going forward

• The courts have taken a narrow approach to construction of force majeure clauses, requiring that obligations have actually become impossible to perform, not merely more difficult or less profitable

The origin of the doctrine of force majeure is the French Civil Code. It has been used as a defence to a claim for breach of contract as in effect it relieves a party of performance because of some ‘act of God ’ or unavoidable catastrophe. A force majeure event may be relied upon if it has made performance of the contract impossible, was unforeseeable and was unavoidable in consequence and effect.

But in English law it is not so simple. The term ‘force majeure’ is not a legal term of art. Chitty describes the normal understanding of the purpose of a force majeure clause as follows:

‘
[a force majeure clause is] normally used to describe a contractual term by which one (or both) of the parties is

entitled to cancel the contract or is excused from performance of the contract in whole or in part, or is entitled to suspend performance or to claim an extension of time for performance, upon the happening of a specified event or events beyond his control.’

Typical force majeure events would include war, riot, civil commotion, strike and natural catastrophes (such as earthquakes and hurricanes) but would not include bad weather, football matches, a funeral or an act, negligence or omission by the party seeking to be excused.

The concept of force majeure cannot be relied upon as a defence unless and to the extent that the contract so provides, or if it is implied as a term. Construction contracts will usually define what is meant by force majeure and the consequences. The precise terms and effect of such clauses can vary widely.

As the leading authority on force majeure in English law (the judgment of McCardie J. in Lebeaupin v Crispin [1920] 2 KB 714) states, the precise ambit of the term will depend on the context in which it is used:

‘A force majeure clause should be construed in each case with a close attention to the words which precede or follow it, and with a due regard to the nature and general terms of the contract. The effect of the clause may vary with each instrument.’

It is common to see force majeure defined by a list of events followed by a general sweep up provision. In Tandrin Aviation Holdings Ltd v Aero Toy Store LLC [2010] EWHC 40 (Comm) the defendant sought to justify its refusal to accept delivery of an aircraft on the basis that the alleged ‘unanticipated, unforeseeable and cataclysmic downward spiral of the world’s financial markets’ constituted ‘any other cause beyond the Seller ’s reasonable control’ as provided for in the force majeure clause of the contract. This, they said, postponed the time for the defendant to complete the purchase.

The judge rejected the argument. He held that this phrase had to be read in the context of the entire clause. Although the judge noted that the phrase ‘any other cause beyond the Seller’s reasonable control’ did not need to mirror the specific examples set out earlier in the definition, he pointed out that it was nonetheless telling that nothing in any of those specific examples was even remotely connected with economic downturn, market circumstances or the financing of the deal.

A force majeure clause may provide relief from liability when a party is prevented from carrying out his obligations or is unable to do so. However, a party seeking to rely on a clause which states that he is relieved of his obligations if he is prevented from carrying them out must show that performance has become physically or legally impossible, and not merely more difficult or unprofitable.

It is not unusual for contractors to claim that whilst performance of the contract is technically possible, it has become financially unviable, so much so, that it is economically impossible.

Generally, a change in economic or market circumstances affecting the profitability of a contract or the ease with which the parties’ obligations can be performed will not be regarded by the courts as constituting a force majeure event. This was the case in Tandrin above.

Thames Valley Power Ltd v Total Gas & Power Ltd [2006] 1 Lloyd ’s Rep 441 established:

‘… It does not at all follow that the supplier is entitled to rely upon an increase in the market price in comparison to the contract price as a force majeure circumstance … This conclusion is consistent with a line of cases, both on force majeure clauses

… to the effect that the fact that a contract has become expensive to perform, even dramatically more expensive, is not a ground to relieve a party on the grounds of force majeure …’

The burden of proof is on the party seeking to rely upon the force majeure clause. He must prove the occurrence of the event he is relying on and that he has been prevented, hindered or delayed (as the case may be) from performing the contract by reason of the event. Subject to the terms of the contract, he must also prove that the event in question was beyond his control and that there were no further steps he could have taken to avoid or mitigate the consequences: Channel Island Ferries Ltd v Sealink UK Ltd [1988] 1 Lloyd ’s Rep 323. In that case a clause that included ‘strikes beyond [its] control’ did not bite if the party seeking to rely on the clause could have settled the strikes by taking reasonable steps.

The standard form construction contracts deal with force majeure differently as illustrated by comparing NEC3, JCT 2011 and the FIDIC Red Book.

NEC3

The term force majeure is not used in NEC3, however cl 19.1 (Prevention) is the equivalent. Clause 19.1 states:

‘ If an event occurs which

• stops the Contractor completing the works or

• stops the Contractor completing the works by the date shown on the Accepted Programme,

and which

• neither Party could prevent and

• an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that

it would have been unreasonable for him to have allowed for it,

the Project Manager gives an instruction to the Contractor stating how he is to deal with the event’.

Such an event is a compensation event (cl 60.1(19)) and a ground upon which the employer may terminate (cl 91.7). Clause 91.7 requires that the event must stop the works completing by the date shown on the Accepted Programme and ‘is forecast to delay Completion by more than 13 weeks.’

The NEC3 Prevention clause is generally regarded as providing a more generous approach for the contractor than a typical force majeure clause, since it puts the onus on the employer to decide how such events should be dealt with and entitles the contractor to both time and money where such events arise. As many employers are uncomfortable with the prospect of considering whether an event is one which it would have been reasonable for a contractor to allow for, these provisions are often deleted by employers, with the result that the contractor may have no effective remedy in the event of force majeure.

JCT

The JCT form clause references are to JCT 2011 With Quantities which includes express reference to force majeure; but it is not defined, which gives rise to potential uncertainty about its scope. In the absence of such a definition Keating on Construction Contracts (9th edn, para 20-118) suggests that the court would follow Lebeaupin v Crispin when attempting to define what a force majeure event would include.

Force majeure is listed as a relevant event which entitles the contractor to an extension of time (cl 2.29.14). It is not identified as a relevant matter for the purposes of recovering loss and expense. It sits alongside other events which could ordinarily be considered as force majeure such as ‘exceptionally adverse weather conditions’ (cl 2.29.9), ‘civil commotion’ (cl 2.29.11), or ‘strike’ (cl 2.29.12).

It may also be a ground for termination (cl 8.11). Clause 8.11.1 provides that if before practical completion, the whole or substantially the whole of the uncompleted works is suspended for the period specified in the contract particulars by reason of various events including force majeure, then either party may give notice of termination.

FIDIC

Clause 19 of the Red Book states:

‘ In this Clause, “ ‘Force Majeure” means an exceptional event or circumstance:

a) which is beyond the Party’s control,

b) which such Party could not reasonably have provided against before entering into the Contract,

c) which, having arisen, such Party could not reasonably have avoided or overcome, and

d) which is not substantially attributable to the other Party.

Force majeure may include, but is not limited to, exceptional events or circumstances of the kind listed below, so long as conditions (a) to (d) above are satisfied:

i. war, hostilities (whether war be declared or not), invasion, act of foreign enemies,

ii. rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war,

iii. riot, commotion, disorder, strike or lockout by persons other than the Contractor ’s Personnel and other employees

of the Contractor and Sub-Contractors,

iv. munitions of war, explosive materials, ionising radiation or contamination by radio-activity, except as may be

attributable to the Contractor ’s use of such munitions, explosives, radiation or radio-activity, and

v. natural catastrophes such as earthquakes, hurricane, typhoon or volcanic activity.’

Read on their own, sub-clauses (a) to (d) could be seen as providing a broad definition of force majeure, however, in line with Lebeaupin v Crispin , reading these with the subsequent sub-clauses I to V may well limit the definition of force majeure.

Clause 19.4 provides that the Contractor can recover an extension of time and can on the occurrence of events I to IV recover cost subject to (in relation to I to IV) these occurring in the country in which the site is located. Clause 19.6 provides that either party may give notice of termination if the execution of substantially all the works is prevented for a continuous period of 84 days by reason of force majeure or for multiple periods totalling more than 140 days.

Summary

These are just examples of some of the standard forms’ treatment of force majeure. It makes sense to consider carefully at drafting stage what parties wish force majeure to look like – as always, it is about who bears the risk. The devil is, as they say, in the detail.

www.dundas-wilson.com

Contract Administration

RECORDS, RECORD, RECORDS – Importance for Contract Claim

Contract Requirement

Max Abrahamson in his book Engineering Law and The ICE Contract wrote

” A party to a dispute, particularly if there is an arbitration will learn three lessons (often too late) the importance of records, the importance of records and the importance of records”. This quotation came to mind recently when I read the judgement in the case of Attorney General for the Falkland islands v Gordon Forbes construction (Falklands) Limited. A contract was let for the construction of the infrastructure of the East Stanley Housing Development in the Falkland Islands using the FIDIC 4th Editions conditions.

…

Contract Administration

The ‘notices’ provision

by Dennis Brand
Many of you will deal with industry-standard form contracts, while others will deal with company standard or even bespoke forms; whatever the form of contract, the notices provision contained in the conditions of contract is probably one of the least-read provisions. The notices provision does not attract the same degree of interest as, say, the variation or change order provisions, or provisions which deal with certificates of completion, suspension or even termination, but in each case a notice is required.

Let me be clear: a notice provision in a contract is not the same as where a contract includes the term ‘notify’; a requirement that one party must inform the other of a thing or matter. A notice provision is where the contract includes the term ‘shall give notice’ (or something similar), which usually requires a formal written notice to be issued by one party and delivered to the other.

For example, a ‘Notice to Proceed’ is a formal notice issued under many forms of industry-standard contracts. The issue of a ‘Notice to Proceed’ is the confirmation that the contractor or supplier of a service is to start work. To proceed on the basis of simply being notified, which could be a phonecall or even a text message, without a formal notice in writing, would be risky in the extreme for the contractor or supplier.

From the employer’s side, such a notice is equally important because, by issuing the formal ‘Notice to Proceed’, he knows that, regardless of what discussions or communications he may have had with the contractor or supplier, they will only start work, and thereby incur cost to his account, once the employer has issued the ‘Notice to Proceed’, and not before.

When one is involved in the preparation of a contract and the subject of the notices provision is to be addressed, there are really six points or matters to be considered:

1. How many days?

The first thing is that the period of notice should be expressed in days rather than weeks. Notice periods will differ depending upon the reason for the notice. When determining the number of days, the period should be reasonable, not too long and not too short, and must be workable. Many contracts contain provisions that, where a contractor seeks additional money or a variation, the contractor must give notice within a limited number of days following the event which resulted in the request. Some contracts go further and provide that, if the notice is not given within the specified time, the contractor loses his right to claim a variation. You may think this pretty harsh, and indeed it is not one that courts or arbitrators like to enforce, but if the period for the notice is reasonable, the contractor should not have any difficulty in complying with it.

2. In what form?

There is no standard form for a notice. The important thing to bear in mind is that it is a standalone document which advises the other party of something or requires the other party to do something. It should contain all the relevant information, including reference to the provision of the contract and relevant clause, so the recipient can be under no misapprehension as to the purpose of the notice and what is required. For example, FIDIC requires that, in the event of a dispute which is referred to the engineer for a decision, the notice must provide a description of the dispute and confirmation that a decision of the engineer under the relevant clause is required. Failure to give that information will likely mean that the notice is considered invalid.

3. Who should sign them?

Due to the importance of a contractual notice, it should only be signed by someone in authority. Rarely will the contract state who should sign the notice. Therefore it should be signed by the same person who signs all other contract correspondence, such as the contractor’s or employer’s nominated representative.

4. To whom should they be sent?

Due to the importance of such a notice, it is important it is brought to the attention of the senior management of the contractor or employer. However, for those large organisations where the head office might be in another country, a notice sent to the head office will not be acted upon at site level until it has been received and site management informed. In order to avoid attendant problems, it is not unusual to see a notice provision which requires the notice to be addressed to a named individual in the head office, with a copy sent to the project manager on-site. I have seen this put to good effect where the employer, who was not getting the required action from the site, issuing a notice, which required the original to be sent to the head office.

5. How should they be delivered?

Usually a notice provision provides for notices to be delivered by one of three methods: by hand, by mail or by fax. To deliver a notice by hand means exactly what is says; it also includes delivery by courier. To include a provision allowing the delivery of a notice by mail, consideration must be given to the delivery point, which could be another country. Often a number of days are added in case of delay, with an overall number of days agreed upon when delivery will be considered as having taken place. For delivery by fax, the sender’s fax report confirms the delivery.

6. Is an acknowledgement needed?

In my view never … that simply invites problems!

CW

Contract Administration

FIDIC 1999 VS FIDIC 1987

By Edward Sunna

What You Need To Know and Why?
The private sector in the UAE and more recently the public sector in Abu Dhabi, have adopted FIDIC or at least a hybrid version of FIDIC for government use. This was done in part to reduce the risk of international contracting, but more importantly, to standardise terms of engagement to reduce uncertainty caused by the application and interplay of Federal Laws and the various Laws of the Emirates, in so far as they are applicable to construction contracts.

…

Construction Law, Contract Administration

FIDIC’S FOUR NEW STANDARD FORMS OF CONTRACT: Risks, Force Majeure and Termination

 By Christopher R. Seppala

I propose briefly to discuss five topics in the three new Books for major works (the new Construction Contract, the Plant Contract and the EPC Contract), as follows:

 (1) Contractor’s risk and “Employer’s Risks”,

(2) Indemnities,

(3) Limitation of Liability,

(4) The New Force Majeure Clause, and

(5) Grounds and Procedure for Termination of the Contract by the Employer and the Contractor. …

Scroll to Top