The Delays We Cause Ourselves: Land, Permits and Utilities on Public Infrastructure Projects

By Dr Samer Skaik

On a large proportion of internationally financed infrastructure projects, the single biggest source of delay is not the contractor. It is the employer’s own inability to hand over the site.

Land that has not been acquired. Households that have not been resettled. A right of way that runs through three private holdings and a cemetery. Electricity poles, water mains and fibre that belong to state-owned utilities with no contractual relationship to the project and no particular urgency about it. An environmental clearance sitting with a regulator that answers to a different minister. Building permits from a municipality that was not consulted during design.

None of this appears in the contractor’s risk register, because none of it was ever the contractor’s to carry. Under the standard forms including FIDIC these are employer obligations, squarely and unambiguously. The contract requires the employer to give the contractor the right of access to and possession of the site, and where it fails to do so within the time required, the contractor is entitled to time and money.

Everyone involved knows this. And yet I have read many project documents in which the delay is described in the passive voice — access was not available, the site could not be handed over — as though it happened weather-like, to nobody in particular. …

Construction Law, Contract Administration, Dispute Boards, Project Management

The Engineer Who Cannot Decide: Contract Administration Inside a Government Approval Chain

B Dr Samer Skaik

There is a moment in project meetings that anyone who works on public infrastructure will recognise.

A question is put to the engineer. It is a fair question, within the engineer’s remit, and the answer is not especially difficult. And before answering, the engineer glances at the employer’s representative sitting across the table.

It lasts less than a second and everybody in the room sees it. The contractor sees it and files it away. The engineer’s own team sees it. And what it communicates is that the person the contract designates as the impartial administrator of this contract is, in practice, checking.

I do not raise this to criticise the engineers involved, most of whom are experienced professionals in an impossible position. I raise it because it is a structural problem specific to public employers, the contract does not solve it, and it is the origin of a startling number of the disputes I see. …

Contract Administration, Dispute Boards, Project Management

The Board You Keep or the Board You Call: A Choice Made Long Before Anyone Argues

By Dr Samer Skaik

There is a box in the contract data of every works contract that gets filled in by someone who will never have to live with the consequences.

It is usually completed late in the tender preparation, often by a procurement officer working through a template under time pressure, sometimes by copying whatever was in the last one. It determines whether the project will have a dispute board sitting alongside it from the beginning, or whether one will be assembled at some future moment when things have gone wrong.

I have asked a number of public officials who made that decision on their project. In most cases the honest answer is that nobody made it. It was inherited. …

Construction Law, Contract Administration, Dispute Boards, Project Management

What Does a Dispute Board Actually Cost? A Straight Answer for Public Employers

By Dr Samer Skaik

Of all the questions I get asked by public sector clients, this is the one that arrives most often by private message rather than in the meeting.

People are slightly embarrassed to ask it. There is a sense that enquiring about the cost of a dispute mechanism is somehow unserious, or that it reveals you have not read something you should have read. So the question gets asked quietly, usually after the formal session has ended, and it is almost always phrased the same way: what does one of these actually cost us?

It is an entirely reasonable question and I wish more people asked it earlier and out loud. A project manager who cannot answer it cannot get the budget line approved, and a budget line that is not approved is one of the most common reasons a board never gets appointed at all. So let me try to answer it plainly. …

Construction Law, Contract Administration, Dispute Boards, Project Management

When the Banks moved onto FIDIC 2017: What Public Employers Inherited With the New Contract

By Dr Samer Skaik

A few years ago I sat in a workshop with the contract management team of a national roads agency. They were good at their jobs. Several of them had been administering donor-funded works contracts for well over a decade, and between them they had probably handled more claims than some law firms see in a generation.

About an hour in, one of the senior engineers said something that stopped the room. He said: we have been running this contract the way we ran the last four, and I am starting to think it is not the same contract.

He was right. It was not. …

Construction Law, Contract Administration, Dispute Boards, Project Management

The First Four Weeks: How Public Infrastructure Employers Set a Project Up to Avoid Disputes

 

By Dr Samer Skaik

The call usually comes about eighteen months in.

Someone from an implementing agency, often a project manager who has inherited the file from a predecessor, explains that things have gone badly wrong. The ground turned out differently from the investigation report. The utility diversions never happened. The contractor has submitted a claim with a number in it large enough that it has now been seen by people several floors above the project office. And somewhere in the conversation comes the question I have learned to brace for: we think the contract requires us to have a dispute board — how quickly can one be set up? …