Construction Law

Construction Law, Contract Administration

Lenders look to limit risks on projects

By David Johnston

Project finance loans are provided against project cash flows, rather than the assets of the project company. Any risk to the project cash flows endangers the lender’s ability to recover the debt capital. The lender, therefore, needs to ensure that the terms of the project documents are satisfactory and will both facilitate and protect the project’s ability to generate the necessary revenue to satisfy the loan repayments, particularly where – as happens all too often – the project runs into difficulties. As part of this, the lender will seek to ensure that the risk allocation between the project company and any third parties is acceptable and, therefore, that the project is considered bankable.

Construction Law, Construction Technology, Procurement Management, Sustainability

Jordan eyes renewable energy

By Katie Liszka

JORDAN is highly dependent on imported energy in the form of natural gas and fuel oil. In 2011, 97 per cent of its energy was imported. The kingdom has also suffered as a result of problems with the supply of gas from Egypt. In addition to its dependency on imported energy, Jordan also projects a high growth in energy demand. Hence, the country has set itself ambitious targets in relation to the introduction of renewables into its energy mix, which will account for at least 10 per cent of the total supply by 2020. There are also a number of individual targets, such as approximately 1,200 MW (megawatts) for wind power and 600 MW for solar.

Construction Law, Contract Administration, Procurement Management, Project Management

Lessons for GCC on concurrent delay

By David Johnston

DELAYS on engineering and construction projects are almost inevitable; the more complex the project, the more likely the prospect of delay, and the more chance of two or more delays occurring at or around the same time.

Where the contractor is culpable for the delay, for example, rectifying its own defective workmanship, it is usually not entitled to an extension of time. However, where an employer-caused delay occurs concurrently with the contractor’s culpable delay – for example, where the employer has instructed a variation, and assuming that each of these events is of approximately equal significance – is the contractor now entitled to an extension of time?

Various legal jurisdictions have struggled with this question and come to different positions. Some of these positions are set out in this article, as are some suggestions as to how this debate should inform approaches taken by employers to concurrent delay on construction projects in the GCC.

Construction Law, Contract Administration, Project Management

Termination for Construction Contracts

By Heba Osman
A common scenario: the Employer is not happy with the Contractor’s performance, whether because of failure to perform the works in the manner provided for in the Contract or because of some other breach of the Contract. The Employer picks up the Contract, which – in the UAE – is usually some modified FIDIC standard form, in search of the termination provision. Most such termination provisions require the Employer to send the Contractor a notice to correct the failure or the breach within a specified period. If the Contractor fails to correct the breach, then the Employer becomes entitled to terminate the Contract. The Employer, feeling confident of its legal position, sends the termination notice. The Employer is satisfied that it has correctly terminated the contract.

Construction Law, Contract Administration

Draft hybrid contract with care

By Martin Preston

TYPICALLY, the contract price under a construction contract will either be a lump sum or cost reimbursable.

Under a lump sum contract, the contractor is required to provide a fixed price for carrying out and completing the scope of work. The risk that the cost of completing the works is more than the lump sum price sits with the contractor, who will only be entitled to be paid more than the lump sum price if the employer varies the scope of the works or delays or obstructs the contractor in carrying out the works. …

Construction Law, Contract Administration

Consultants’ Fee Claims To Be Time-Barred in the UAE

By Michael Grose

As the fifth anniversary of the onset of the financial crisis approaches, engineers, architects and other consultants to the construction industry should be aware of the potential risk that this unhappy anniversary presents to any remaining fee claims. Whilst any expectation of payment at this late stage is likely to be low, any optimism that early signs of returning confidence might provide a chance to cash in old debts should take into account one of the more obscure time limits applicable under UAE Laws. …

Construction Law, Contract Administration, General Management, Project Management

Construction Law Summer School – IBC Legal’s 13th Annual Conference

“An international fiesta for construction industry professionals.”

 Join your international peers at IBC Legal’s most comprehensive construction law event for 3 days of intensive learning and networking

Construction Law Summer School – IBC Legal’s 13th Annual Conference

3rd – 5th September 2013 – Downing College, Cambridge University, UK

CMguide readers get a 10% saving …

Construction Law

Recent Ruling Of Dubai Court Of First Instance On Enforcement Of Foreign Arbitral Awards: Back To Square One?

by Gordon Blanke

A recent ruling of the Dubai Court of First Instance (see Case No. 489/2012, ruling of the Dubai Court of First Instance of 18 December 2012) questions de novo the UAE courts’ compliance with their obligations under international enforcement instruments in the enforcement of foreign arbitral awards. Following the recent trend of consolidation of the UAE courts’ practice to abide by the terms of international enforcement instruments – foremost amongst them the New York Convention (see Convention on the recognition and enforcement of foreign arbitral awards, done in New York on 10 June 1958, as ratified and hence implemented in UAE law by UAE Federal Decree No. 43 of 2006), this ruling marks a sudden and unwelcome setback in what commentators had believed had become a turning-point in the UAE enforcement practice of foreign arbitral awards. …

Scroll to Top