Construction Industry

Construction Industry, Construction Law, Contract Administration, Project Management

Decoding Concurrent Delay: The SCL Protocol and Employer Responsibility

Delays in construction and infrastructure projects are almost an inevitability. But what happens when multiple delays hit at once, and some are the client’s fault while others lie with the contractor? This is the tricky terrain of concurrent delay, a concept that can lead to significant disputes over extensions of time and financial compensation.

The Society of Construction Law (SCL) Delay and Disruption Protocol (2nd Edition, 2017) stands as a beacon of guidance in this often-murky area. While not a legally binding document in itself, it’s widely respected and often referenced by courts and tribunals as best practice for resolving delay and disruption claims.

Let’s dive deep into what the SCL Protocol says about concurrent delay, particularly when the employer is a contributing factor, and how this impacts a contractor’s entitlements.

What is Concurrent Delay, Really? The SCL’s Refined View

Before the SCL Protocol, “concurrent delay” was a term thrown around with varying interpretations. The Protocol, however, offers a much-needed clarification, distinguishing between “true” concurrency and delays with “concurrent effects.” This distinction is crucial for understanding entitlements.

  • True Concurrent Delay (Rare Beast!): Imagine two separate, independent events. Event A is an Employer Risk Event – perhaps the client failed to provide approved drawings on time. Event B is a Contractor Risk Event – the contractor suffered a major equipment breakdown. If both of these events occur simultaneously and each independently causes delay to the critical path of the project, then you have true concurrent delay. The SCL Protocol acknowledges this as genuinely rare. Why? Because in most projects, delays tend to have ripple effects rather than perfectly synchronized, independent origins.
    • External Perspective (FIDIC): While the SCL Protocol offers a detailed definition, it’s worth noting that international contract forms like FIDIC (Fédération Internationale Des Ingénieurs-Conseils) often deal with concurrent delay through a “but for” test – essentially asking if the contractor would have been delayed anyway by their own events, even without the employer’s delay. This can sometimes lead to different outcomes than the SCL’s approach.
  • Delays with Concurrent Effects (The Common Scenario): This is where most “concurrent delay” scenarios actually fall. Here, an Employer Risk Event might happen, and then later, a Contractor Risk Event occurs, or vice-versa. However, at some point, their effects on the critical path overlap. The key here is that both events, irrespective of their start dates, become critical path delays during the same period.
    • Example: The employer delays providing access to a work area for two weeks (Employer Risk). Later, due to poor planning, the contractor runs into a labor shortage for three weeks, impacting the same critical path activities that were already pushed back by the access delay (Contractor Risk). For a period, both delays effectively impact the same critical path.

The SCL Protocol emphasizes that for a delay to be truly “concurrent” or have “concurrent effects” in a way that impacts entitlements, both delay events must be on the critical path to completion. A delay to a non-critical activity, even if occurring at the same time as a critical path employer delay, does not constitute concurrency in the context of EOT or loss and expense.

Entitlements in the Face of Concurrent Employer Delay: Time and Money

This is where the rubber meets the road. How do you allocate responsibility and adjust the contract when the employer is a cause of delay during a period of concurrency? The SCL Protocol offers clear guidance, treating extensions of time (EOT) and financial compensation (loss and expense) differently.

1. Entitlement to Extension of Time (EOT): The “Prevention Principle” Reigns Supreme

 

When an Employer Delay to Completion occurs concurrently with a Contractor Delay to Completion, the SCL Protocol generally advocates for the contractor to receive a full Extension of Time for the entire period of the Employer Delay.

  • The Rationale: The Prevention Principle. This principle, a cornerstone of English contract law, dictates that an employer cannot benefit from their own breach of contract or act of prevention. If the employer’s actions (or inactions) contribute to the project being delayed, they cannot then hold the contractor liable for not finishing on time.
  • No Apportionment for EOT: Crucially, the SCL Protocol states that the contractor’s own concurrent delay should not reduce the amount of EOT granted for the employer-caused delay. If the employer caused a critical delay, the contractor gets that time back, irrespective of their own concurrent delay.
    • Clarification (Scottish Law): While the SCL Protocol is broadly accepted in the UK, it’s worth noting that in Scottish law, the “apportionment” approach (where EOT might be split if delays are truly concurrent) has sometimes been favored by courts. This highlights the importance of the governing law of the contract. However, the SCL Protocol’s strength lies in its practical, common-sense approach to fairness.
  • Practical Impact: This means if a project is delayed by 30 days due to the employer’s late design information, and during those 30 days, the contractor also experiences a 15-day delay due to their own poor planning on a critical path activity, the contractor would still likely receive a 30-day EOT. The employer’s delay set back the contractual completion date by 30 days, and the contractor should not be penalized for that.

2. Entitlement to Compensation (Loss and Expense): The Cost Conundrum

While the SCL Protocol is generous with EOT during concurrent delay caused by the employer, it takes a more stringent approach to financial compensation (prolongation costs, or “loss and expense”).

  • No Automatic Compensation: The Protocol advises that the contractor is not automatically entitled to recover additional costs during a period of concurrent delay where both employer and contractor delays are critical.
  • The Burden of Proof: For compensation, the contractor must demonstrate that they incurred additional costs solely due to the Employer Delay that they would not have incurred anyway due to their own concurrent delay.
  • Separating Costs: This often requires the contractor to meticulously separate and prove which costs were directly caused by the employer’s delay. If the contractor would have incurred certain overheads or site establishment costs anyway because their own delay would have kept them on site for that period, then they cannot claim those specific costs from the employer.
    • Example: Following the previous example (30-day employer delay, 15-day contractor delay within that period), the contractor gets a 30-day EOT. However, for loss and expense, they would need to prove which, if any, of their additional site overheads or prolongation costs were exclusively due to the employer’s 30-day delay, and not to the 15-day period where their own delay would have kept them on site regardless. This can be incredibly difficult to prove in practice.
  • Why the Difference? The rationale is that while the employer should not prevent the contractor from completing on time (hence the EOT), the employer also shouldn’t pay for the contractor’s inefficiency or delays that would have occurred regardless.

Beyond the Definitions: Practical Application and Best Practices

 

The SCL Protocol isn’t just about definitions; it’s about practical application. Here are some key takeaways for all parties involved:

  1. Contemporaneous Records are King: The ability to prove delay and its causes hinges entirely on excellent, up-to-date project records. Daily diaries, meeting minutes, progress photographs, resource allocation sheets, and updated programmes are invaluable.
  2. Regular Programme Updates: A well-maintained and regularly updated project programme (or schedule) is critical. It allows for a clear, contemporaneous assessment of the critical path and how various events are impacting it.
  3. Proactive Communication: Early identification and communication of potential delays, whether by the employer or the contractor, can help mitigate their impact and facilitate resolution.
  4. Expert Delay Analysis: In complex cases, engaging a specialist delay analyst who understands the SCL Protocol and various methodologies is often essential. They can conduct a forensic analysis of the project programme and records to determine causality and concurrency.
  5. Contractual Clarity: While the SCL Protocol provides guidance, the contract itself remains paramount. Parties can choose to adopt alternative approaches to concurrent delay within their contract clauses. Always refer to the specific terms of your agreement.

Conclusion

 

The SCL Delay and Disruption Protocol provides a clear, rational, and widely accepted framework for navigating the treacherous waters of concurrent delay. By distinguishing between true concurrency and delays with concurrent effects, and by taking a nuanced approach to EOT versus financial compensation, it aims to achieve a fair outcome that respects the prevention principle while also holding contractors accountable for their own performance.

Understanding and applying the SCL Protocol’s principles can significantly reduce disputes, foster clearer communication, and ultimately contribute to the successful delivery of construction projects, even when the inevitable delays occur.


Construction Industry, Construction Law, Contract Administration

The Critical Edge: Why Early Warning Notices Matter in FIDIC 2017

Unforeseen events and potential issues are almost inevitable in construction and infrastructure projects. How these challenges are identified, communicated, and addressed can significantly impact a project’s success, cost, and timeline. The FIDIC 2017 suite of contracts places a strong emphasis on proactive risk management and dispute avoidance, with the Early Warning Notice (EWN), specifically under Sub-Clause 8.4 [Advance Warning], being a cornerstone of this philosophy.

This post dives into the rationale and utility of Early Warning Notices under FIDIC 2017, exploring what happens if these provisions are not complied with, and outlining the responsibilities of all parties when such a notice is issued. …

Construction Industry, Construction Law, Contract Administration, Statutory Adjudication

Beyond Battles: How Dispute Boards Transform Construction Conflict into Collaboration

In the complex world of construction and large-scale infrastructure projects, effective dispute resolution is paramount to keeping ventures on track and budgets intact. While traditional methods like litigation and arbitration have their place, the rise of Dispute Boards (DBs) offers a proactive and often more efficient alternative. These independent bodies aim not just to resolve disputes, but, crucially, to manage and even prevent them from escalating, acting as an integral part of project delivery. …

Construction Industry, Construction Law, Contract Administration

The Challenging Role of the Engineer/CA/PM in Construction Dispute Resolution

Disputes are an inevitable byproduct of complex projects, involving multiple parties, intricate contracts, and high stakes. At the heart of managing these conflicts, often with a heavy and unenviable burden, stands a key figure: the Engineer, Contract Administrator (CA), or Project Manager (PM).

Their role, as defined by various standard forms of contract, is often multifaceted, requiring them to be simultaneously technical experts, project leaders, financial custodians, and, crucially, initial dispute resolvers. It’s a tightrope walk where impartiality is expected, but practical realities often tug them towards one side. …

Construction Industry, Construction Law, Contract Administration, Security of Payment, Statutory Adjudication

Your First Strike: Why Adjudication is the Ultimate Opening Move in Construction Disputes

In the high-stakes, fast-paced world of construction, disputes are not a matter of “if,” but “when.” From payment disagreements and extension of time claims to quality issues and unforeseen ground conditions, conflicts are an inherent part of managing complex projects. When these disputes inevitably arise, how you choose to address them can be the difference between project success and crippling delays or financial ruin. …

Construction Industry, Construction Law, Contract Administration, Procurement Management, Project Management

Level Up Your Construction Contract Knowledge: Introducing the CMGuide Podcast Series!

The world of construction contracts, especially the globally recognized FIDIC suite, can often feel like navigating a complex labyrinth. Clauses, entitlements, claims, termination rights, dispute boards… it’s a lot to keep track of, even for seasoned professionals. But what if you could demystify these crucial topics, one engaging conversation at a time, right from your headphones?

We’re thrilled to announce the launch of the CMGuide Podcast Series!

This isn’t just another dry lecture. We’re bringing you in-depth, practical discussions designed to unpack the intricacies of construction contracts, with a special focus on the FIDIC Suite of Contracts. …

Construction Industry, Construction Law, Contract Administration, Project Management

Mastering Disruption Claims: Insights from FIDIC 1999 and 2017

Construction projects, by their very nature, are susceptible to disruptions – events that hinder the regular and efficient progress of work, leading to a loss of productivity and increased costs. While delays extend the project timeline, disruption impacts the efficiency of work within that timeline, often without necessarily extending the overall completion date. Successfully navigating disruption claims is crucial for contractors to recover legitimate losses and for employers to understand their contractual obligations. This post explains disruption claims under two prominent FIDIC (Fédération Internationale Des Ingénieurs-Conseils) contract editions: FIDIC 1999 and FIDIC 2017, highlighting their differences, how to establish entitlement, and methods for quantifying associated costs or Extension of Time (EOT).

Construction Industry, General Management, Sustainability

Gen AI: Your Ally or Your Downfall? Making It Work for You

By Dr Samer Skaik

Generative AI is everywhere these days. It’s like having a super-smart assistant who can whip up a report or summarise a journal article in seconds. For professionals chasing deadlines and students grinding through assignments, AI can feel like a lifeline. But it’s not all smooth sailing. Lean on it too much, and you might lose your spark. Ignore it, and you could get left behind. This article is about finding the sweet spot—using AI to boost your game without letting it take over. Let’s unpack how to stay sharp, stay sceptical, and keep ahead of the curve. …

Construction Industry, Construction Law, Contract Administration, Project Management

How Dispute Boards Operate Under FIDIC Contracts: A Guide in a Nutshell

Construction projects are complex, high-stakes endeavors where disputes can derail timelines, inflate budgets, and strain relationships. The International Federation of Consulting Engineers (FIDIC) provides a robust solution through its globally recognized standard contracts, which integrate Dispute Boards (DBs) as a cornerstone for conflict management. This educational blog post dives deep into the mechanics of Dispute Adjudication Boards (DABs) and Dispute Avoidance/Adjudication Boards (DAABs) under FIDIC’s 2017 Rainbow Suite, focusing on their appointment, proactive dispute avoidance, and resolution roles. Guided by FIDIC’s 2024 and 2023 Practice Notes, relevant provisions of the FIDIC 2017 contracts, and industry insights, we explore how DBs contribute to successful project delivery.

Construction Industry, Construction Law, Contract Administration, Project Management

Empowering the Engineer: Significant Advances in FIDIC 2017 Red Book Over 1999

The FIDIC Red Book, published by the International Federation of Consulting Engineers (FIDIC), is a widely used standard form of contract for construction projects where the Employer designs the works. The role of the Engineer, a pivotal figure in administering the contract, has undergone significant enhancements in the FIDIC 2017 Red Book compared to its 1999 predecessor. These improvements aim to promote fairness, clarity, and efficiency in contract administration. This blog post explores the key advancements in the Engineer’s role under FIDIC 2017, focusing on substantial changes and citing relevant clauses for educational purposes. For brevity, we will not dwell on aspects of the Engineer’s role that remain unchanged or have only minor differences between the two editions. …

Construction Industry, Construction Law, Contract Administration, Project Management

Understanding FIDIC Golden Principles: A Guide for Construction Professionals

In this post, we dive into the FIDIC Golden Principles, a cornerstone of fair and balanced construction contracts globally. Whether you’re a contractor, engineer, or project manager, understanding these principles is essential for navigating international construction projects with confidence. Let’s explore what they are, why they matter, and how they impact your work.

Construction Industry, Construction Law, Security of Payment, Statutory Adjudication

Judicial Decisions Concerning Expert Evidence in Adjudication

By Dr Samer Skaik

In the realm of construction disputes, expert evidence plays a pivotal role in shaping the outcomes of litigation and arbitration. Traditionally, expert witnesses are engaged by parties to analyze facts, form opinions, and present conclusions that can influence the decision-making process of a tribunal. However, the growing use of expert witnesses in statutory construction adjudications, especially for large and complex payment claims, has introduced new challenges. Unlike the more extended timelines in litigation and arbitration, adjudicators in construction disputes often operate under severe time constraints—typically just 10 business days. This accelerated process leaves little room for the thorough examination of expert evidence, such as cross-examinations or detailed meetings with experts, which can complicate the adjudication process. …

Scroll to Top