Author name: CMGuide

Construction Law, Contract Administration

Contemporary records

It is not often that I will get the opportunity to report a case from the Falkland Islands Supreme Court, but the case of Attorney General for the Falkland Islands -v- Gordon Forbes Construction deals with a point of general interest in the management of claims.

Forbes had entered into a contract with the Falkland Islands government for the construction of the infrastructure of the East Stanley Housing Development in the Falkland Islands. The contract was based upon the FIDIC Conditions of Contract for Works of Civil Engineering Construction, 4th Edition.

Construction Law, Contract Administration

Can disputes be settled like gentlemen?

By Dr Chandana Jayalath

In Qatar’s public works, the employer and the engineer mostly operate as the same entity, although they are two different entities in the strict contractual sense.

As such, the dispute clause, which is available in any typical infrastructure project in Qatar, generally considers both the employer and the engineer as one party to the dispute. This may be why the dispute clause talks about disputes between employer or engineer and the contractor. …

Construction Law, Contract Administration

Time At Large

Whenever there is delay in a construction project, parties immediately look to the liquidated damages clause. This is understandable, as the Contractor carries the risk of delay resulting from events for which it is responsible, and that risk is usually quantified by the provision of liquidated damages.
However, where such events are caused by an act or omission by the Employer, the Employer bears the risk. In such event, unless there is a clear mechanism for extending the time for completion, the Employer’s right to levy liquidated damages will fall away.
It is for this reason that most standard form contracts usually provide for an extension of time mechanism which allows for the time for completion to be extended upon an event of prevention or impediment by the Employer. The purpose is primarily to enable the Employer to protect its right to potential liquidated damages in the event of its own default. …

Contract Administration

CMGuide is the Media Partner for the 3rd FIDIC Middle East Contract Users’ conference

FIDIC’s 2012 conference is your annual opportunity to get best practice advice on using the FIDIC contracts and updates on the contract changes and amendments – directly from the very people who drafted them!
GMGUIDE readers can get a 10% discount by with VIP code: FKW82257CMGL

Taking place on the 22nd & 23rd February 2012 in Doha, attend for advice on:

Selecting the most relevant form of contract; cost management; the FIDIC Construction Contract & new Construction Subcontract; the Plant & Design Build, EPC/Turnkey and DBO Contracts; claims under FIDIC Contracts; application of FIDIC Conditions of Contract in the Middle East; the new FIDIC Procurement Procedure Guide; DAB procedures, arbitration, ADR and more!  Find out more on the newly released agenda. …

Construction Law, Contract Administration

FIDIC’s Middle Eastern Contract Users’ conference returns for a 3rd year!

This is your annual opportunity to get best practice advice on using the FIDIC contracts and updates on the contract changes and amendments – directly from the very people who drafted them!

Get a 10% discount with VIP code: FKW82257CMGP1 – and if you book by the end next Thursday 15th December you’ll get the lowest early bird prices as well. …

Project Management

Estimating a Project for Planning Purposes

When a project or collection of projects is in the idea or concept stage, you want to put together a high-level estimate to see whether or not the project is worth pursuing. You typically do not want to spend too much time working on a detailed estimate at this point, since you do not know if the idea is a worthwhile. Basically, you just want to know the relative magnitude of the effort. While you may be asked to provide a high-level estimate of the cost, the business people are also struggling to try to understand and quantify what the benefits of the project will be. …

Construction Law

BIM raises liability and copyright issues

By KATIE LISZKA

Building information modelling (BIM) is being used increasingly across the construction industry as a tool to reduce costs and encourage good communication and coordination between project participants. It has been used in the US for several years and its use is now spreading across the globe. For example, it has been used by GHD architects on the Palm Jebel Ali project in Dubai, UAE. …

Project Management

Work on the Project Charter, Schedule and Budget Simultaneously

There is not necessarily sequential order between defining (planning) the project and building the schedule and budget. That is, you do not have to completely define the work first and then build the schedule and budget second. Some of the sections of the Project Charter, such as the estimates for cost and duration, cannot be completed without starting to lay out the overall project schedule. …

Contract Administration

Variations in Construction Contracts

Variations in Construction Contracts

Variations in construction contracts can mean changes to the terms of the contract or it can mean changes to the scope or character of the works. In this article, Lim Chuen Ren looks at variations in construction contracts in the latter sense.

Variations to the scope of construction works are necessary because no project is impeccable and changes are required to meet unforeseen circumstances or changed requirements. Thus, variation can be in the form of additions, omissions or substitutions.

Functions of Variations Clauses

Variation clauses are a common feature in construction contracts. It is useful to note, at the outset, that the proprietor is not entitled as of right to direct variations (Ashwell Nesbitt v Allan & Co (1912) Hudson’s Building Contracts (4th ed) Vol 2 at page 462). Hence the need for a variation clause. Secondly, they ensure that contractors can recover payments for variations properly directed (Knight Gilbert Partners v Knight (1968) All ER 248).

Issues Concerning Variation

Broadly, problems concerning variations arise in three areas:

scope (was it a variation or was the contractor bound to do it anyway?);
non-compliance with procedural requirements; and
valuing the variations.
Whether the variation work is within the scope of the contract will depend, firstly, on the terms of the contract, which sometimes beg the question: what is the contract? In many cases, the documents forming the contract are defined. An example is clause 1.1 of PC-1 (PC-1, 1988 Project Contract by Property Council of Australia) which provides:

Contract

The contractual relationship between the parties is constituted by:

(a) the Formal Agreement to which these Conditions of Contract are attached;
(b) these Conditions of Contract;
(c) the Contract Particulars;
(d) the Works Description; and
(e) the other documents (if any) referred to in the Contract Particulars.

Even without such explicit provisions, it is probably true to say that the court will not confine itself to the written agreement alone in determining the scope of the contract: specifications, drawings, correspondence, etc, all form part and parcel of the contract.

Having determined the contract documents, there is the further issue of inconsistencies in or between parts of the contract. Different contracts deal with the issue differently. FIDIC, in clause 5(2), provides for a priority list of documents as follows:

The several documents forming the Contract are to be taken as mutually explanatory of one another, but in the case of ambiguities or discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the contractor instructions thereon and in such event, unless otherwise provided in the contract, the priority of the documents forming the contract shall be as follows:

(i) The contract Agreement (if completed).
(ii) The Letter of Acceptance.
(iii) The Tender.
(iv) Part II of these conditions.
(v)  Part I of these conditions.
(vi) Any other document forming part of the Contract.

The JCC-D 1994 contract (section 2, JCC-D 1994 Building Works Contract without Quantities issued by the Joint Contracts Committee, Australia) provides for a similar precedence of contract documents but goes one step further by requiring the contractor or architect, if they discover any discrepancy, to inform the other. The architect will then give to the contractor an instruction explaining, determining or correcting the discrepancy.

Implied or Necessary Works

As indicated, whether a particular work is a variation will depend on whether it comes within the general scope of the contract. Some works, although not specifically described, are nevertheless considered as implied or form a necessary part of the contract. An early case on this point is Williams v Fitzmaurice (1858) 157 ER 709. In that case, the contractor undertook to provide ‘the whole of the material mentioned or otherwise in the foregoing particulars necessary for the completion of the work’ and ‘to perform all works of every kind mentioned and contained in the foregoing specifications for the sum of 100.00 pounds’. Flooring was not specifically mentioned and the issue was whether it was included in the contract. The court held that it was.

Similarly, in Walker v Randwick Municipal Council (1929) SR (NSW) 84 the contractor agreed to ‘do and perform the whole of the works required in or about the construction of a concrete retaining wall’. In performing the works, Walker had to remove a sandbank to construct the retaining wall. The plan (which was not incorporated in the contract) showed the bank to be 6 feet wide. Walker claimed the bank was in fact 12 feet wide and claimed for work and labour in removing the extra 6 feet. The majority of the court held that the contract was an entire one to build a retaining wall at a fixed price and that the risk lay with contractor. Rogers J said (at page 87):

The contract is not to perform the work set out in any plan; all work necessarily required for the construction must be done whether set out in the plan or not.

Formal Requirements – Written Directions

A variation is usually effected through an instruction from the principal’s architect or superintendent. Such instructions are usually required to be in writing. Whether this is a pre-requisite to the contractor’s right to recover payment will depend on whether the requirement is a condition precedent. This is a matter of interpretation of the contract. Lord Blackburn in District Road Board of Broadmeadows v Mitchell (1867) 4 WW & A’B (L) 101 (FC) has this comment:

It is common enough to have provisions, as these are here, more or less stringent, saying that no extra work shall be paid for unless it is ordered in writing by the engineer, and if such conditions are properly made, and there is nothing fraudulent or iniquitous in the way they are carried out, these conditions would be quite sufficient and effectual (Tharsis Sulphur & Copper Co v M’elvoy & Sons (1878) 3 AC 1040 at pages 1050-1051).

What constitutes ‘writing’ is sometimes also an issue. In Wormald Engineering Ltd v Resources Conservation Co (1992) 8 BCL 158, sketches in the architect’s office describing the variations to be done was held not to be sufficient to satisfy the clause requiring alterations to be directed in writing in the architect’s hand, but in Bedford v Borough Of Cudgegong (1900) 16 WN (NSW) 142, a letter signed by the architect authorising the work was held to be sufficient.

Recovery in the Absence of a Written Direction

Whilst failure to comply, on the whole bars, a claim, there have been cases where courts have allowed the contractors to recover on the basis of an implied promise to pay: Liebe v Molloy (1906) 4 CLR 347, or estoppel: Update Constructions Pty Ltd v Rozelle Child Care Centre (1990) 20 NSWLR 251, or on the basis of unjust enrichment – standing by and taking the benefits: Hill v South Staffs Railway (1865) 12 LT (NS) 63, or on the basis that the works ordered are outside the scope of the contract and, therefore, constitutes a separate contract: Pavey & Mathews v Paul (1987) 61 ALJR 151.

Limitations on the Power to Vary

Variation clauses, even if widely drafted, nevertheless have limitations. One such limitation is the issuance of the practical certificate of completion. Commissioner of State Bank v Constain (1983) 3 ACLR 1 illustrates the point that the power to order variations is not in force after the certificate of practical completion as it then reaches the stage for maintenance and rectification of defects. This restriction is now reflected in AS 4000 Clause 40.

Secondly, the contractor is not required to undertake works that are outside the scope of the variation clause itself. As Cook J in J & W Jamieson Construction v City Of Christchurch (unreported, 8 November 1984, Christchurch High Court) said:

To my mind, if a variation may fairly be said to be a change to the works as these described, whether it comprised an addition, reduction or substitution to the works or effects the carrying out of the works, then it is a variation which the contractor is under an obligation to carry out, if it is beyond that, it is not.

A third limitation that is sometimes canvassed is this. A variation is defined as something which bears some relationship to the current contract works (Blue Circle Industries plc v Holland Dredging Co Ltd 37 BLR 40 per Purchas LJ). Thus, the variations directed must be ‘of a character and extent contemplated by, and capable of being carried out under, the provisions of the contract’ (AS 4000 Clause 36.1). A similar qualification is to be found in the JCCD 1994 Contract, Clause 6.10.01 (‘Unless otherwise agreed all Variations shall be within the general scope of this Agreement so as to be of a character and extent contemplated by and capable of being executed under the applicable conditions of this Agreement.’). Clauses like these prevent the proprietor from effecting fundamental changes to the building design or works under the guise of variations.

Other limitations relate to the right of the proprietor to omit works from the contractor. Generally, the power to vary the scope of works does not allow a proprietor to deprive the contractor of the benefit of that work altogether. In Commissioner of Main Roads v Reid [1974] 131 CLR 378 (see also JA Berriman v Carr (1953) 89 CLR 327), a clause in the contract allowed that:

if sufficient topsoil to meet the requirements of the works cannot be obtained within the right-of-way, the engineer may direct the contractor in writing to obtain top soil from other approved locations.

The contract also contained a clause allowing the engineer to omit any of the works. The engineer, instead of allowing the contractor to obtain the required topsoil from other approved locations, decided to omit the works from the contractor and awarded the works to another contractor, at a cheaper rate. The High Court of Australia held that the clause only gave the engineer the choice between directing the contractor to obtain the topsoil or to omit the works. It did not confer on the engineer the right to have the works performed by a third party.

Stephen J (at page 382) made the point that:

Were he [the engineer] legally entitled to do so it would, I think, run counter to a concept basic to the contract, namely that the contractor, as successful tenderer, should have the opportunity of performing the whole of the contract works.

Chadmax v Hansen & Yunken Pty Ltd (1985) BCL 52 is a case that illustrates the dilemma sometimes faced by the main contractor when compelled by the proprietors to omit certain works. In this case, the subcontractor was engaged to install ‘wallflex’ to stairwells and corridors. The architect subsequently deleted a substantial portion of that particular work from the main contract and the main contractor did likewise with the subcontract. The subcontractor sued the main contractor for repudiation of contract and succeeded. The judge in the first instance, Brebner J, commented that:

I would have held that the power in the defendant to require increases or decreases in or omissions from the sub-contract work or changes in the character or quality of any material a work could not be construed as a power to cancel virtually the whole of the subcontract works.

The main contractor joined the owners as a party to the action but, unfortunately for the main contractor, the ‘wallflex’ works in the main contract constituted only a minor part and their omission from the main contract was held to be within the general scope of the contract.

Valuing the Variation

If the variation falls within the terms of the contract, the rates prescribed will be used to value the work. Clause 36.4 of AS 4000 is one such clause, which also allows a reasonable sum for profits:

36.4 Pricing
The Superintendent shall, as soon as possible, price each variation using the following order of precedence:

prior agreement;
applicable rates or prices in the contract;
rates or prices in a priced bill of quantities, schedule of rates or schedule of prices, even though not contract documents, to the extent that it is reasonable to use them; and
reasonable rates or prices, which shall include a reasonable amount for profit but not overheads.
That price shall be added to or deducted from the contract sum.

In most cases, valuation using the rates prescribed in the contract presents no real problem. But what is the position if the contract is terminated or if the works are carried out under a separate, and usually oral, contract? In such cases, the courts will usually award a reasonable rate or a rate on a quantum meruit basis. As Giles J said in Atlantic Civil Pty Ltd v Water Administration Ministerial Corpn (unreported, 16 October 1992, NSW Supreme Court):

… [A] variation was to be valued in accordance with schedule rates so far as applicable or, in the absence of agreement, by determining a reasonable rate a price. No doubt the referee considered that the Schedule rates were inapplicable, and when he referred to ‘a quantum meruit basis under the contract’ I consider that he meant a reasonable sum for the additional work. Thus, the referee was not assessing a sum outside and in defiance of the contract. In my opinion the defendant’s submission was based on a misconception of the report.

Conclusion

Variation is almost an inevitable part of any construction claim. Given the competitive environment that the construction industry is usually in, many contractors probably rely on the proprietor’s variations to make a reasonable return for their contracts. In addition, variation works commonly affect the completion date and, therefore, impact on delay claims by the proprietor. This explains, to some extent, why the resolution of issues concerning variations is never easy, especially if the dispute is heard way after the building is completed and records are scarce, making physical measurement of the works completed difficult.

Lim Chuen Ren
CR Lim Construction Lawyers, Melbourne

Scroll to Top