Contract Administration

Contract Administration

Common contractual concerns

Michelle Nelson, partner, Pinsent Masons, says it is worth examining five common traps before plunging into construction in Dubai.

Let’s examine some of the potentially troublesome issues which contractors face regularly in the Dubai construction market. In preparing this article I have highlighted five issues which we are asked to advise contractors on regularly. …

Contract Administration, Project Management

What should Clients do when dealing with one tenderer only?

By Samer H Skaik

Sometimes, clients face difficulty to procure projects due to absence of competitors. The risk of how to secure value for money is extremely high when dealing with one single contractor to quote and execute the works. This article gives significant guidelines for which client can follow to minimize such risk and achieve value for money:

1. Give priority for traditional accelerated procurement route:

By adopting this route, the contractor is appointed early during the design stage based on partial information made available by Design team. Due to early involvement in design stage, the contractor can add a significant input to the design and improve the billability since he is the only specialist who can carry out such works. This involvement will somehow ensure value for money.

  1. Give intensive care to design development stage:

Design should be sound, efficient and integrated to avoid variations risks in construction stage which will affect the price certainty due to possible design errors, additions and omissions. Client advisor needs to supervise the design development precisely as first step to ensure value for money ad reasonable cost certainty. On the other hand, budget estimate should be done by the consultant upon the completion of brief design based on historical data. It should typically have an accuracy of 10% to 15% (Keith, 2008).

3. Go for single tendering process: (Negotiated – No competition)

In such scenario, the client should go for single tendering in which it approaches the contractor directly to quote for the project. Negotiation skills must be mainly adopted to ensure the price is as minimal as possible to secure the value for money. This process does require experienced clients and consultants to have influence on the contractor to reduce his price (Turner, 1997).

Effective procedures during the single tendering process must be adopted with the contractor to reach to a satisfactory level prior to sign the contract as follows (Marsh, 2000):

  1. The client must inform the contractor of his intention to award the project on a single tender basis provided that the contractor shows cooperation in this regard. It is not advisable at all to deceive the contractor by inviting him to tender and give the impression that many other contractors are involved. This will definitely kill the confidence and affect the future negotiation process.
  1. Formal agreement should be made with the contractor to consider his formal involvement in the project based on preliminary design and on the basis of negotiation.
  1. Once design completes, the contractor should be requested to submit his firm prices based on all available information such as specifications, drawings, etc.
  1. Technical agreement and programme of work should be secured prior to the commercial negotiation.
  1. General and special conditions of contract should be forwarded to the contractor to consider them in assessing the risk and considering it in his price.
  1. The contractor is to be instructed to prepare his detailed estimates as per the general practice. This estimate will be initially evaluated by comparing it with the estimated allocated budget.

4. Start the negotiation procedures to secure the value for money:

There are basically two methods to negotiate the price (Marsh, 2000):

ü  Simple Comparison Measures:

In this method, some priced items of the contractor are compared with similar ones known to the consultant from previous recent competitive tender. In this project, the difficulty arises when it seems to be impossible to compare any of the items on apple to apple basis, since the nature of the whole project is unique.

ü       Alternative method:

The contractor will be instructed to submit detailed break down of his firm prices separating out the markup and preliminaries from the dry cost. The dry cost will be separated into labour, material, equipment and vendors with precise quantities of each item.

Alternative method seems more suitable to be adopted in this project and further discussion of costs and prices can commence as follows (Marsh, 2000:

  1. Once the alternative method is completed, brought in items and material can be checked against the relevant quotations or current market rates. It should be noted whether the vendor quotations are discounted or not. Labour costs and productivity can be easily checked and evaluated as per the country normal wage rates and productivity.
  1. Construction method statement should be submitted to allow the client to check how the contractor will distribute his resources and combine them especially the plants. This is a significant factor in assuring that the prices are realistic.
  1. Overheads, profit and contingencies should be negotiated and reasonably agreed. Negotiation skills play major role in this part to get the maximum reduction in the percentage.
  1. Payment terms should be discussed in detail. It directly affects the pricing, since the contractor assesses his cash flow and the financial charges associated with reduced revenue. Since the project funding is available, the client is recommend to agree on relaxed interim payment to enhance the cash flow, which will result in cutting some costs.
  1. Liquidated damages should be addressed and agreed. Client should make sure that the liquidated damages are appropriate since the timing is a critical aspect in this project.
  1. Once all above procedures are performed and agreed, the contractor should submit a final lump sum fixed price tender.
  1. Once the client issues the letter of acceptance, the contract exists and considered as if it resulted from normal competitive tendering. Any gain or loss by the contractor during construction should be dealt away from the client.

5. Improve price certainty by transferring risks:

It is recommended to transfer the potential risks such as the price escalation risk and bad weather to the contractor to secure price certainty. This can be achieved by appropriate wording in the contract clauses. The criteria is to transfer the risks to party best able to handle it which comes in line with the objective of value for money as well. However, it is unwise to transfer a risk to the contractor if it is difficult to assess (Mudoch & Hughes, 2000).

6. Appoint the same designer to supervise the construction stage:

Consultant who made the design is recommended to play supervising and monitoring role during construction to ensure the high quality and smooth progress. He will be effective in making the sound decisions in case of any design query raised during construction.

7. Suggest target cost contract as an alternative approach:

It is possible that the contractor objects to go for the lump sum contract following the above procedures. In this case the client can suggest going for cost plus contract incorporating target cost and guaranteed maximum price. Target cost will be derived from the pre-contract budget and cost plan. Maximum value for money can be secured by the project team by trying to reduce the costs as far below the target cost as possible (Morledge, Smith, Kashiwagi, 2006). Moreover, cost certainty can be reasonable in presence of realistic GMP. This approach can be effective by applying share gain/pain policy and open book accounts.

References:

1.       Keith, P. (2008), Construction Cost Management: Learning from Case Studies, Routledge

2.       Turner, A. (1997), Building procurement, (second edition), Palgrave macmillan, London.

3.       Marsh, P. (2000), Contracting for Engineering and Construction Projects,(Fifth Edition), Gower Publishing.

4.       Morledge, R., Smith, A. and Kashiwagi D. (2006), Building procurement, Blackwell Publishing, Oxford.

5.       Mudoch, J., Hughes, W. (2000), Construction contracts law and management, third edition, Spon press, New York.

Contract Administration

Building relationships in joint venture projects

by Kristine Kalnina
 
Kristine Kalnina, Bin Shabib and Associates.Looking at any of the impressive structures shaping Dubai’s skyline, one may see just glass and steel as the main constituent components. But all projects stem from an idea before they become tangible objects and that idea heavily depends on first building successful relationships. …

Construction Law, Contract Administration, Contractual Adjudication

Benefiting from a DAB resolution

By Hamish Macdonald
 
In the first place, DABs are not intended to replace arbitration or litigation but are to be considered as part of a multi-tiered dispute resolution process. The use of a DAB has been described as an early and intermediary step directed at avoiding the need to resort to other more expensive and more time-consuming procedures such as arbitration or litigation. …

Contract Administration

Understand the Characteristics of Quality for Your Project

It is hard to define product or service quality at a high level because the term “quality” is nebulous and means different things to different people. You must take the time to define the lower-level characteristics of quality for each specific service or deliverable. If you want to ensure that a service or product meets the customer’s expectations of quality, you have to understand the underlying characteristics of quality. …

Contract Administration

Advising clients on the appropriate form of contract

In some procurement contexts, the choice of contract may be determined by external factors, such as requirements of the funder. For example the World Bank now require the FIDIC forms of contract to be used on projects of over £6 million, and it appears as if the NEC form may be the preferred choice for the Olympic construction programme. In such cases the form to be used will have been selected before the Architect and other consultants are appointed. …

Contract Administration

Create a Short-Term Schedule to Guide the Definition and Planning Processes

The process of creating the Project Charter, schedule and budget may take a long time and may be very complicated. Therefore, the work should not be left unorganized, for the same reasons that you are building the schedule for the project to begin with. Immediately after being assigned, the project manager should create a short-term schedule to plan and guide the initial activities. …

Contract Administration

Estimating Effort

Effort hours must be estimated first, before duration and cost estimates can be prepared. Use the following process to estimate effort hours.

1. Determine how accurate your estimate needs to be.

Typically, the more accurate the estimate, the more detail you need to understand about the project, and perhaps the more time that is needed. If you are asked for a rough order of magnitude (ROM) estimate (-25% – +75%), you might be able to complete the work quickly, at a high level, and with a minimum amount of detail. Perhaps you can provide a ROM estimate based on knowledge in your head. On the other hand, if you must provide an accurate estimate within 10%, you need to spend more time and understand the work at a lower level of detail.

2. Create the initial estimate of effort hours

Estimate each activity and for the entire project, using techniques described in 2.2.1 Estimating Techniques.

3. (optional) Factor the effort hours based on the resources assigned

Your estimates are probably based on the effort it will take an average resource to do the work (or perhaps the estimates are based on the effort it would take if you did the work). Sometimes you also have knowledge of the exact resource or the type of resource that will be assigned. If you do, you may want to factor the estimate up or down. For instance, you may estimate an activity to take 40 effort hours. However, you also know that the person who will do the work is an inexperienced trainee. In this case, you may want to double the estimate to 80 hours. Another set of activities may be estimated to take 200 hours. However, you know that you will hire an experienced contractor to do the work, so you may be comfortable reducing the estimate to 150 hours. Obviously, this step can only be performed if you have some sense for the actual resources to be applied to the project.

4. Add specialist resource hours

Make sure you have included hours for part-time and specialty resources. This could include freelance people, training specialists, administrative help, etc. These are people that may not be obvious at first, but you may need them for special activities.  Because they are typically in project support roles, you may have forgotten to include their activities in the original Work Breakdown Structure.

5. (optional) Add rework time

In a perfect world, all project deliverables would be correct the first time. On real projects, that usually is not the case. Schedules that do not consider rework can easily end up underestimating the total effort involved with completing deliverables.

This is not to be confused with scope changes. If you produce a deliverable that does not meet all the original requirements, or has a quality problem, then rework may be required. If the original deliverable is not acceptable because of additional requests for new features, functions or requirements, then scope change management should be utilized. There are a number of ways to factor in the effort and time associated with rework.

  • Add into the original estimate. This is probably the most typical approach. If you think that a deliverable will take 50 hours to complete, you may be already be considering the work required for one set of corrections, or maybe two.
  • Add as separate activities. In this approach, you estimate the effort of completing the deliverable the first time, and then add a second set of activities, effort and duration for making corrections and recycling a second (and third) time through.
  • Add as blocks of time. Rather than add rework to individual deliverables, add a block of time at the end of a phase for rework. This is basically adding a general budget and schedule buffer to help absorb the rework time associated with a group of deliverables. The effort and cost associated with the buffer could be based on individual rework estimates or just a percentage of the original deliverable development time.

6. Add project management time

Project management takes effort and there is an associated cost as well. You need to allocate effort hours to successfully and proactively manage a project. You should add 15% of the effort hours for project management. For instance, if a project estimate is 12,000 hours (7 – 8 people), then a full-time project manager (1800 hours) is needed. If the project estimate is 1,000 hours, the project management time would be 150 hours. This would not be enough for a full-time project manager, so the project manager would either be a part-time project resource or the project manager would also have non-project management activities assigned to him as well.

7. Add contingency hours

Contingency is used to reflect the uncertainty or risk associated with the estimate. If you are asked to estimate work that is not well defined, you may add 50%, 75% or more to reflect the uncertainty. If the estimate was required on short notice, a large contingency may be required. Even if you have time to create a reasonably accurate estimate, your contingency may still be 10-25%. If you do not add a contingency amount, it would mean that you are 100% confident in your estimate. This may be the case if similar types of projects have been done before.

When you add contingency, the best approach is to include it as a separate line item. However, if your organization will not allow you to include a formal estimating contingency, you may have no choice but to include the estimating contingency by padding the estimates of all the underlying activities. This is not the preferred approach, but it is the natural reaction if your organization will not allow a formal estimating contingency budget to reflect estimating uncertainty.

8. Calculate the total effort

Add up the estimates for all the work components described above.

9. Review and adjust as necessary

Sometimes when you add up all the components, the estimate seems obviously high or low. If your estimate does not look right, go back and make adjustments to your estimating assumptions to better reflect reality. Also make sure that your estimating model is consistent and reasonable. For instance, if a repetitive activity is planned, you might initially calculate the total effort by multiplying the effort to complete one activity by the number of times the activity is executed. However, upon further evaluation, you may realize that the effort to complete the activity will decrease as it becomes routine. You should also make sure that similar activities have similar effort estimates and if they do not, adjust them as needed.

10. Document all assumptions

You will never know all the details of a project for certain. Therefore, it is important to document all the assumptions you are making along with the estimate.

Tenstep.com

Scroll to Top