Contractual Adjudication

Construction Law, Contract Administration, Contractual Adjudication

Unveiling the Veil: The Complex Role of Superintendents and QS in Construction Projects

By Dr Samer Skaik

In the intricate dance of construction projects, the roles of superintendents and financier-appointed quantity surveyors (QS) are central yet often enveloped in complexity. These roles are critical in maintaining contractual integrity and financial oversight. However, their independence and impartiality are subjects of ongoing legal scrutiny. This post delves into the delicate balance these professionals must maintain, guided by insights from landmark legal cases.

The Facade of Independence: A Closer Look at Financier’s QS

Typically, a financier’s appointed QS serves to safeguard the financier’s interests, providing reports and recommendations on the project’s financial health. However, their role does not extend to certifying progress payments in accordance with the contract. This was notably discussed in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Limited [2002] NSWCA 211, where it was emphasized that the QS acts as an advisor and agent to the financier, not as an unbiased or independent certifier of progress claims.

The Superintendent’s Balancing Act

Superintendents or principal representatives administer the building contract between the principal and the builder. Their role is to perform contract administration functions, including the certification of payment claims and variations fairly, reasonably, and in good faith. The necessity for impartiality and fair dealing in this role has been underscored in multiple cases. For example, Scheldebouw v St. James Homes (Grosvenor Dock) Ltd [2006] BLR 113 established that under such contractual arrangements the principal’s agent or partner acting as a superintendent is prohibited. Similarly, Kane Constructions Pty Ltd v Sopov [2005] VSC 237 provided a set of criteria indicating potential interference with a superintendent’s independent certification functions, including undue influence or control by the principal.

Intersecting Duties and Conflicts: Real-world Implications

The real-world implications of these roles are far-reaching, especially when individuals find themselves wearing multiple hats within the same project. The dual role of a principal representative and developer, for instance, raises significant conflict of interest concerns. This conflict was analogously addressed in Walton v Illawarra [2011] NSWSC 1188, highlighting the inevitable bias in certification and the real possibility of conflict. The case serves as a poignant example of the challenges faced when maintaining neutrality in complex project environments.

Judicial Guidance and the Path Forward

The courts have consistently provided guidance on these contentious issues, ensuring that the roles of superintendents and QS are executed with the utmost integrity. For instance, Vestas – Australian Wind Technology Pty Ltd v Lal Lal Wind Farm Nom Co Pty Ltd [2020] VSC 554 illuminated the risks associated with conduct that might compromise the superintendent’s duty of independence, emphasizing the importance of transparent and independent certification.

Conclusion

The roles of superintendents and financier-appointed QS in construction projects are fraught with challenges, demanding a high standard of professionalism and ethical conduct. By examining landmark cases and understanding the judicial guidance provided, professionals can navigate these roles more effectively, ensuring fairness and integrity in construction projects. It’s not just about legal compliance; it’s about upholding the trust and dependability that is foundational to successful construction projects.

Construction Law, Contract Administration, Contractual Adjudication, Statutory Adjudication

Adjudication is future of dispute resolution

By STUART JORDAN

The future is adjudication. Its benefits are being seen in more regions globally, and governments everywhere are enacting legislation for a mandatory right of adjudication in construction disputes.

Well, not quite everywhere.

In the Gulf region, we have not seen much take up of adjudication as is provided for in standard Fidic (Fédération Internationale des Ingénieurs-Conseils, French for International Federation of Consulting Engineers) contracts nor enactment of the statutory version. …

Construction Law, Contract Administration, Contractual Adjudication, Project Management

Can A Party Be Prevented From Referring A Dispute To Adjudication?

By Shona Frame

FIDIC Conditions require the contractor to give notice of a claim for extension of time (EOT) not later than 28 days after the contractor became aware, or should have become aware, of the event or circumstances giving rise to the claim. The Technology and Construction Court (TCC) in London has recently adopted a relaxed interpretation of this requirement. …

Construction Law, Contract Administration, Contractual Adjudication

Adjudication in The Middle East

By Nicolos Gould
Adjudication is now a dispute resolution process that most in the UK construction industry are familiar with. The process was introduced by the Housing Grants, Construction and Regeneration Act 1996, which became effective from May 1998. We have therefore lived with it for almost 15 years. Adjudication is included in all of the standard form contracts, but in any event will be implied, as we all now know, into any contract that meets with the definition of “construction contract” under the Act.

Other common law countries have followed suit. All of the states in Australia now have security of payment legislation, which introduces a right to adjudication. New Zealand is the same. Singapore also introduced a Security of Payment Act which provides for adjudication. Malaysia introduced a similar Act providing for adjudication in June 2013, and it is due to be in force soon. Other countries have considered similar legislation. The mechanics of the legislation varies between countries and states, but they all share the desire to provide a rapid, binding dispute resolution procedure.

The situation in the Middle East is somewhat different. There has been considerable construction work in that region for many years. The wealth created by oil has led to increasing levels of development throughout the region. Dubai is perhaps the best known for its substantive impressive developments such as The Palm and The Burj Khalifa Tower. Despite a slowdown of construction activity 4 years ago, as a result of the economic crisis, Dubai has continued to grow. The Dubai Theme Park is now under way, along with many other substantial developments.

Dispute resolution in the region and in Dubai has provided some challenges. The local courts have been unfamiliar with complex construction contracts, and local employers have not always been keen to agree to use international arbitration. International arbitration is of course widely used throughout the world for substantial projects involving suppliers and contractors from countries other than the one where the work is taking place. Nonetheless, Dubai has a regional arbitration centre in the form of the Dubai International Arbitration Centre (DIAC) and also the Dubai International Financial Centre (DIFC). Egypt has for some time had an arbitration centre in Cairo, and now Qatar also has the Qatar International Centre for Conciliation and Arbitration (QICCA). However, international arbitration can be time-consuming and expensive.

It is perhaps then unfortunate that adjudication has not been introduced by local legislation within the Middle East. However, that would require a cultural understanding not just of the locals from the Middle East, but also the international contractors and consultants who work there. Both have a different perspective on how disputes are resolved. Why should the international community impose upon the Middle East a rapid dispute resolution procedure, which in commercial terms is quite new to the business community even by international standards? Perhaps it is something that will be considered and debated over time.

On the other hand, dispute boards have been used in the region in some instances. They are not necessarily the norm, but through the use of FIDIC, dispute adjudication boards and dispute review boards have been encountered.

The use of the term “Dispute Boards” or occasionally “Disputes Boards” (collectively DBs) is relatively new. It is used to describe a dispute resolution procedure which is normally established at the outset of a project and remains in place throughout the project’s duration. It may comprise one or three members who become acquainted with the contract, the project and the individuals involved with the project in order to provide informal assistance, provide recommendations about how disputes should be resolved and provide binding decisions. The one-person or three-person DBs are remunerated throughout the project, most usually by way of a monthly retainer, which is then supplemented with a daily fee for travelling to the site, attending site visits and dealing with issues that arise between the parties by way of reading documents and attending hearings, and producing written recommendations or decisions if and as appropriate.

The term has more recently come into use because of the increased globalisation of adjudication during the course of projects, coupled with the increased use of Dispute Review Boards (“DRBs”), which originally developed in the domestic USA major projects market. DRBs were apparently first used in the USA in 1975 on the Eisenhower Tunnel. The use of DRBs has steadily grown in the USA, but they have also been used internationally. However, DRBs predominantly remain the providence of domestic US construction projects. As adjudication developed, the World Bank and FIDIC opted for a binding dispute resolution process during the course of projects, and so the Dispute Adjudication Board (“DAB”) was born from the DRB system; the DRB provides a recommendation that is not binding on the parties.

The important distinction then between DRBs and DABs is that the function of a DRB is to make a recommendation which the parties voluntarily accept (or reject), while the function of a DAB is to issue written decisions that bind the parties and must be implemented immediately during the course of the project. The DRB process is said to assist in developing amicable settlement procedures between the parties, such that the parties can accept or reject the DRB’s recommendation. Building upon this distinction, the International Chamber of Commerce (ICC) has developed three new alternative approaches:

1. Dispute Review Board – the DRB issues recommendations in line with the traditional approach of DRBs. An apparently consensual approach is adopted. However, if neither party expresses dissatisfaction with the written recommendation within the stipulated period then the parties agree to comply with the recommendation. The recommendation therefore becomes binding if the parties
do not reject it.

2. Dispute Adjudication Board – DAB’s decision is to be implemented immediately.

3. Combined Dispute Board (“CDB”) – this attempts to mix both processes. The ICC CDB rules require the CDB to issue a recommendation in respect of any dispute, but it may instead issue a binding decision if either the employer or contractor requests, and the other party does not object. If there is
an objection, the CDB will decide whether to issue a recommendation or a decision.

According to the ICC the essential difference is that the parties are required to comply with a decision immediately, whereas the parties must comply with a recommendation but only if the employer and contractor express no dissatisfaction within the time limit. The combined procedure seems at first glance to be a somewhat cumbersome approach, attempting to build upon the benefits of the DRB and DAB, without following a clear pathway. Nonetheless, it may prove useful for those parties that cannot decide whether they need a DRB or a DAB.

At the other end of the spectrum a DB could be considered as a flexible and informal advisory panel. In other words, before issuing a recommendation, the DB might be asked for general advice on any particular matter. The DB will then look at documents and/or visit the site as appropriate and, most usually, provide an informal oral recommendation which the parties may then choose to adopt. If the parties were not satisfied, the DB would proceed to the issue of a formal, albeit non-binding, written recommendation after following the formal procedure of exchange of documents and a hearing. Perhaps this amicable approach will suit the Middle East more than a rapid, binding adjudication process.

Construction Law, Contract Administration, Contractual Adjudication, Project Management

Why is Amicable Settlement a Part of Contractual Machinery?

By Dr. Chandana Jayalath
Disputes occur when parties fail to address conflicts of their interests as they often attempt to find solutions within the bounds of the contract where the rights and obligations are typically set out. Forgetting the fact that contracts are not ‘water proofed’, parties tend to limit their scope of thinking within the hard bound copies. The reality is that contracts do not operate in a vacuum. A contract that caters to all eventualities is indeed rare, so that parties will have to turn to another side, willingly or unwillingly, for a settlement. This is why negotiation has become a day to day phenomenon. …

Construction Law, Contract Administration, Contractual Adjudication

Dispute boards: the missing link?

   Leonora Riesenburg.

After the Dispute Review Board (DRB) Foundation and Society of Construction Law (Gulf) met to discuss dispute boards and their function in the local market, many praised the ‘checks and balances’ proffered by the mechanism.

The rationale behind the dispute board is simple. The DRB provides a non-binding recommendation to contracting parties that have appointed a board of three independent experts, intended to comb out difficulties either prior to the offset of, or in answer to, a problem.

A similar principle applies to the Dispute Adjudication Board (DAB), save that the DAB’s decision has interim-binding force.
Dispute boards have been given tour de force by the active support of the Dispute Board Federation, the Dispute Resolution Board Foundation, ICC, and standard-form contract authorities including the International Federation of Consulting Engineers (FIDIC).

This form of independent regulation has had a warm welcome in the West. Interestingly though, collaboration contracts such as NEC have been tested in territory, most notably by Abu Dhabi’s Aldar Properties in the early phases of Al Raha Beach Development, and failed to take flight.

Creating valuable opportunities for periodic review is fine in theory. In practice, however, it is rare that two parties’ agendas will be aligned in such a way as to capitalise on the opportunity.

Competing interests are a particular concern when more than two parties are involved. Returning control to the employer and the contractor is only worth the paper it is written on to the extent that the employer and contractor play ball.

In the case of long-term appointments, a day rate, allowances and disbursements customarily need to be shouldered for all three board members, over the course of the life of the project, however lengthy. The cost implications can be staggering.

The fact of the matter is that employers will never want to pay above a budgeted figure for the contracted services, and service providers will be bent to do their utmost to secure their minimum margin.

The equation only ever balances if the margin for error is not eroded. Commercial reality dictates that errors are made and a price tag is attached to each of them. It is the allocation of these risk events, and in turn its cost, that is the bone of contention among contracting parties.

The effectiveness of an independent administration, in the form of dispute boards, in the context of this tension, is questioned.

The UAE has been slow to apply FIDIC 1999, calling for the appointment of a DAB as part of its dispute process. If and when adopted, the standard conditions are often heavily modified and reinstate the engineer’s traditional role as a de facto ‘dispute manager’.

Further the language of contracts in territory is slow to entertain the admissibility of recommendations or resolutions in any subsequent arbitration or legal suit.

When legal fees are calculated on a percentage fee basis, irrespective of complexity, the mathematical exercise rapidly dwarfs the financial benefits attributed to the DB.

The Abu Dhabi Municipality has moved the markers further afield with its Municipality Construction Contract, essentially a heavily modified form of the 1999 FIDIC Contract for Construction, by making it mandatory for a ‘standing’ DAB to be appointed once a dispute has arisen.

A ‘standing’ DAB is in effect a half-way house. Where the Municipality Contract gives on one hand, it takes on the other: the engineer’s role in dispute resolution is re-assigned to the employer.

One would not need to go into any further detail to entertain that dispute boards, particularly given their limited application in territory, are not a means to an end.

There is no real replacement for proper internal administration coupled with continuous sound legal counsel and guidance to complement to the day-to-day workings of commerce.

CW

Construction Law, Contract Administration, Contractual Adjudication

Benefiting from a DAB resolution

By Hamish Macdonald
 
In the first place, DABs are not intended to replace arbitration or litigation but are to be considered as part of a multi-tiered dispute resolution process. The use of a DAB has been described as an early and intermediary step directed at avoiding the need to resort to other more expensive and more time-consuming procedures such as arbitration or litigation. …

Scroll to Top