Construction Claims
by Sarah Thomas
Question:
I am a project manager for the employer on a power plant project based in Europe. We have been on quite good terms with the contractor up until now. Last week the contractor sent us a claim for 12 weeks’ delay to the programme and for compensation costs (we are using the FIDIC Yellow Book (Plant and Design Build) 1999 form and English governing law). They are saying that dealing with contamination in the ground discovered in the last few weeks will cause a delay. We had a couple of site meetings with the contractor and sub-contractor about the programme and the potential delays, prior to the contractor sending the claim. I have two issues with the claim: firstly, we do not believe that the ground conditions will cause 12 weeks’ delay; our estimate would be closer to about 6 weeks. Secondly, the contractor’s written notice of claim is just a couple of lines in an email to me and I am not sure this counts as proper “notice”.
I do not want to jeopardise our relationship with the contractor, but obviously I am concerned to limit our exposure to any delay costs. I would appreciate any advice about how we can deal with this claim from our contractor.
…